About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

13 Const. L. Int'l 7 (2018-2019)
Adding the Best Bits of FIDIC 2017 to the 1999 Forms

handle is hein.journals/cnstrcnl13 and id is 239 raw text is: 











ADDING THE BEST BITS
OF  FIDIC   2017  TO  THE
1999   FORMS
Edward Corbett
Corbett & Co International Construction
Lawyers, London

Much has been said about the second
editions of the Red, Yellow and
Silver Books launched by FIDIC in
December  2017. The most obvious
comment  has been about their size,
almost 50,000 words, which is some 60
per cent longer than the 1999 forms.
  Although  the 1999 forms were
not  perfect, most regular users
seem   to   agree  that   20,000
additional words were not needed
to fix the issues. This consensus led
this author to attempt to cherry-
pick the useful provisions of the
2017    forms    and    propose
amendments   to add  these good
ideas to  the  1999 forms.  The
amendments   apply  to all three
forms unless otherwise indicated.


Reasonable   profit

Any  reduction  in the number
of  occurrences   of  the word
'reasonable' is to be applauded,
given the scope for argument that
the word  introduces. The World
Bank  introduced a definition of
reasonable profit into its documents
and  the Pink Book  Multilateral
Development  Bank form.
1.2 Add:   '(e)  references   to
    reasonable profit shall mean
    the percentage of Cost stated
    in the Appendix to Tender.'
    Add  to Appendix  to Tender:
    'Reasonable profit... 1.2(e)...
    -  per cent or, if none is stated,
    5 per cent.'


Approval  for engineer's actions

The 1999 forms did not make clear
whether the employer could insist on
pre-approving determinations under
Sub-Clause 3.5. Many assumed they
could not, but FIDIC's guide to the
1999 form said otherwise. The 2017


forms put the matter beyond doubt,
introducing a new requirement for
the engineer to act 'neutrally' when
making determinations.
3.1 Add  in the third paragraph
    after 'undertakes': 'not  to
    require   approval   for  a
    determination   under   Sub-
    Clause  3.5 [Determinations]
    and'.
3.5 Red  and Yellow only: replace
    'the Engineer  shall consult'
    with 'the Engineer  shall act
    neutrally and shall consult'.


Prompt   notice of variations

The  1999 drafters slipped up by
not explicitly requiring prompt
notice of instructions that the
contractor   considers   to  be
variations. This has led to problems
with unhappy  employers blaming
their engineers for inadvertently
incurring additional costs. The
notice requirement gives employers
and  engineers an opportunity to
reconsider an instruction.
3.3 Red and Yellow - add after the
    second   sentence:  'If  the
    Contractor considers that an
    instruction  constitutes  a
    Variation, the Contractor shall
    immediately,   and    before
    commencing   any work related
    to the instruction, give a notice
    to the Engineer with reasons.
    If  the Engineer  does  not
    respond    within  7    days
    confirming,   revoking   or
    varying the  instruction, the
    Engineer shall be deemed  to
    have revoked the instruction.'
3.4 Silver -  add  after second
    sentence: 'If the Contractor
    considers that an instruction
    constitutes a Variation, the
    Contractor shall immediately,
    and  before commencing  any
    work related to the instruction,
    give a notice to the Employer
    with reasons. If the Employer
    does not respond within 7 days
    confirming,   revoking   or
    varying the  instruction, the
    Employer  shall be deemed to
    have revoked the instruction.'


Definition  of fitness for
purpose

The 1999 form required the works to
be fit for the purposes as defined in
the contract. This caused problems
when  secondary elements  of the
work did not function properly. The
primary purpose of the project may
have been defined, but no one will
define the purpose of each and every
element, rendering the fitness for
purpose obligation less than useful.
So some general wording is needed.
4.1 Red   -  add   to  (c) after
    'Contract': '(and each element
    of the part shall be fit for its
    ordinary purpose)'.
    Yellow and Silver - add at end
    of   first paragraph   after
    'Contract': '(and each element
    of the Works shall be fit for its
    ordinary purpose)'.


Cap  on delay  damages

It seemed  anomalous   that the
limitation of liability in Sub-Clause
17.6 should not apply in cases of fraud,
and so on, but that the cap on delay
damages  should apply regardless.
Some contractors exploited this when
the delay damages had reached their
maximum,   and the employer had
no realistic option of termination:
resources were transferred to other,
more  profitable projects and there
was little that the employer could do.
8.7 Add  at the end  of the first
    paragraph: 'other than in the
    case  of  fraud,  deliberate
    default or reckless misconduct
    by the Contractor'.


Enforcement   of dispute
adjudication  board  (DAB)
decisions

It was a major shortcoming of the
1999 forms that there was no clear
sanction where a party, usually the
employer, failed to pay amounts
awarded  by the DAB. Despite the
obligation to comply  set out in
Sub-Clause  20.4, there was little
that the party winning the DAB
could do; and thus little incentive


CONSTRUCTION LAW INTERNATIONAL Volume 13 Issue 4 January 2019

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Short-term subscription options include 24 hours, 48 hours, or 1 week to HeinOnline.

Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most