B-422471,B-422471.2 Jul 02, 2024 1 (2024-07-02)

handle is hein.gao/gaoqnt0001 and id is 1 raw text is: U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                       Comptroller General
Washington, DC 20548                                 of the United States
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to
Decision                           a GAO Protective Order. This redacted version has
been approved for public release.
Matter of:  National Aerospace Solutions, LLC
File:     B-422471; B-422471.2
Date:     July 2, 2024
Scott M. McCaleb, Esq., Jon W. Burd, Esq., Cara L. Sizemore, Esq., and Sarah B.
Hansen, Esq., Wiley Rein LLP, for the protester.
Andrew E. Shipley, Esq., Philip E. Beshara, Esq., Jessica S. Aldrich, Esq., and Jarrod
R. Carman, Esq., Wilmer Cutler Pickering Hale and Dorr LLP, for Beyond New
Horizons, LLC, the intervenor.
Colonel Christine C. Piper, Michael J. Farr, Esq., Major Roza S. Sheffield, Gregory B.
Porter, Esq., Ryan A. Mueller, Esq., and Lieutenant Colonel Jeffrey J. Hannon,
Department of the Air Force, for the agency.
Glenn G. Wolcott, Esq., and Christina Sklarew, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST
1. Agency reasonably determined that awardee's proposal was superior to protester's
proposal under the most important evaluation factor, technical, based on the agency's
determination that awardee's proposal offered greater benefits under three of the four
equally weighted subfactors.
2. Agency reasonably evaluated the quality of protester's performance under the
predecessor contract as very good--but not exceptional, and reasonably concluded
that the protester's and awardee's proposals were essentially equal under the past
performance evaluation factor.
3. Agency reasonably evaluated the cost realism of awardee's proposal where the
agency considered multiple aspects of the offerors' cost/price proposals, including
proposed labor hours, labor rates, and total evaluated costs.
DECISION
National Aerospace Solutions, LLC (NAS), of Reston, Virginia, protests the Department
of the Air Force's award of a contract to Beyond New Horizons, LLC (BNH), pursuant to
request for proposals (RFP) No. FA910122RB001, to provide test operations and
sustainment services for the Arnold Engineering Development Complex (AEDC)

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most