B-422272,B-422272.2 Mar 15, 2024 1 (2024-03-15)

handle is hein.gao/gaoqch0001 and id is 1 raw text is: 



                    U.S. GOVERNMENT   ACCOUNTABILITY OFFICE
441 G St. N.W.                                                   Comptroller General
Washington, DC 20548                                              of the United States

                                             DOCUMENT   FOR PUBLIC RELEASE
                                           The decision issued on the date below was subject to
DecisionI                                  a GAO Protective Order. This redacted version has
     D ecision                             been approved for public release.


Matter of:   General Dynamics  Information Technology, Inc.

File:        B-422272; B-422272.2

Date:     March 15, 2024

Noah  B. Bleicher, Esq., Moshe B. Broder, Esq., Andrew L. Balland, Esq., and Sierra A.
Paskins, Esq., Jenner & Block, LLP, for the protester.
J. Andrew Jackson, Esq., Ryan P. McGovern, Esq., Robyn B. Celestino, Esq., and
Shelbie Rose, Esq., Jones Day, for International Business Machines Corporation, the
intervenor.
Michelle S. Bennett, Esq., Lisa DeBolt, Esq., and Karen DeBolt, Esq., Department of the
Navy, for the agency.
April Y. Shields, Esq., and Christina Sklarew, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST

1. Protest challenging the agency's cost realism evaluation, which found the protester's
proposal materially noncompliant with the solicitation, is denied where the evaluation
was reasonable and consistent with the terms of the solicitation and applicable
procurement  law and regulation.

2. Protest challenging the agency's decision not to conduct discussions is denied
where the solicitation provided that the agency intended to make award without
discussions and no statute or regulation required the agency to conduct discussions.

3. Protest challenging the agency's cost realism evaluation of the awardee's proposal is
denied where the evaluation was reasonable and consistent with the terms of the
solicitation and applicable procurement law and regulation.

4. Protester is not an interested party to raise other challenges to the agency's
evaluation and award decision where, due to being materially noncompliant under the
cost evaluation factor, it would not be eligible for award.
DECISION

General Dynamics  Information Technology, Inc., (GDIT) of Falls Church, Virginia,
protests the issuance of a task order to International Business Machines Corporation

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most