B-421942,B-421942.2,B-421942.3 Dec 13, 2023 1 (2023-12-13)

handle is hein.gao/gaopqg0001 and id is 1 raw text is: 



                   U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                            of the United States

                                            DOCUMENT   FOR PUBLIC RELEASE
                                          The decision issued on the date below was subject to
Decision                                  a GAO Protective Order. This redacted version has
                                          been approved for public release


Matter of:  VSE  Corporation

File:     B-421942; B-421942.2;   B-421942.3

Date:        December  13, 2023

Grant H. Willis, Esq., Fernand A. Lavallee, Esq., Ryan P. McGovern, Esq., and Robyn
B. Celestino, Esq., Jones Day, for the protester.
Jason A. Carey, Esq., J. Hunter Bennett, Esq., and Andrew R. Guy, Esq., Covington &
Burling LLP, for Amentum Services, Inc., the intervenor.
Laura A. Whitten, Esq., Christopher Lybeck, Esq., Trenton Bowen, Esq., and Robert M.
Jusko, Esq., Department of the Navy, for the agency.
Samantha  S. Lee, Esq., and Peter H. Tran, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST

1. Protests challenging cost realism analysis and the agency's evaluation under the
management   factor are denied where the record shows that the agency complied with
the solicitation's terms.

2. Protest that the agency failed to perform a proper best-value tradeoff is denied
where the agency's award decision was reasonable and adequately documented.
DECISION

VSE  Corporation, of Alexandria, Virginia, protests the Department of the Navy, Naval
Sea Systems  Command's  award  of a contract to Amentum Services, Inc. of
Germantown,  Maryland, under request for proposals (RFP) No. N0002418R4200 for
foreign military sales (FMS) follow-on technical support (FOTS). VSE argues that the
agency's evaluation of proposals and resulting award decision were improper.

We  deny the protest.

BACKGROUND

On July 5, 2019, using the procedures of Federal Acquisition Regulation (FAR) part 15,
the Navy issued the solicitation on an unrestricted, full and open competitive basis.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most