B-297172 1 (2005-12-01)

handle is hein.gao/gaocrptaqzh0001 and id is 1 raw text is: 




A         G    A    O                                                   Comptroller General
.       Accountability * Integrity * Reliability                         of the United States
United States Government Accountability Office       DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                   The decision issued on the date below was subject to a
                                                       GAO Protective Order. This redacted version has been
                                                       approved for public release.

          Decision

          Matter of: FN Manufacturing, Inc.

          File:        B-297172; B-297172.2

          Date:        December 1, 2005

          John S. Pachter, Esq., Jonathan D. Shaffer, Esq., Erin R. Karsman, Esq., Richard C.
          Johnson, Esq., and David S. Stern, Esq., Smith Pachter McWhorter & Allen, for the
          protester.
          Jeffrey I. Kessler, Esq., and Maria B. Bribriesco, Esq., Department of the Army, for
          the agency.
          Ralph 0. White, Esq., and Christine S. Melody, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Protest challenging an agency's affirmative determination of the awardee's
          responsibility on the ground that there is evidence raising serious concerns that the
          contracting officer (CO) unreasonably failed to consider available relevant
          information suggesting that the awardee does not have a satisfactory record of
          integrity and business ethics is denied where the record shows that: (1) while the
          awardee was investigated for possible fraud, it was neither indicted nor proposed for
          debarment; (2) the CO was aware of the information that led to the questions about
          the awardee's activities under certain previous contracts and did not ignore the
          matter; and (3) the CO's more recent dealings with the company provided a rational
          basis for her conclusion that the awardee is a responsible contractor.
          DECISION

          FN Manufacturing, Inc. protests the award of a contract to Tri-Technologies, Inc.
          under solicitation No. W52H09-05-R-0190, issued by the Department of the Army for
          12,500 bipod assemblies for M249 machine guns. FN challenges the Army's
          affirmative determination of Tri-Tech's responsibility.


We deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most