B-415994,B-415994.2 1 (2018-05-14)

handle is hein.gao/gaobaduqq0001 and id is 1 raw text is: 



GO U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                             of the United States
                                          .......................................................................................................................
                                             DOCUMENT FOR PUBLIC RELEASE
                                           The decision issued on the date below was subject to
Decision                                   a GAO Protective Order. This redacted version has
                                           been approved for public release.


Matter of:   Alliant Solutions, LLC

File:        B-415994; B-415994.2

Date:        May 14, 2018

Lee P. Curtis, Esq., Seth H. Locke, Esq., and Andrew J. Victor, Esq., Perkins Coie LLP,
for the protester.
James H. Roberts III, Esq., Van Scoyoc Roberts PLLC, Smartronix, Inc., for the
intervenor.
Kelli Cochran-Seabrook, Esq., General Services Administration, for the agency.
Stephanie B. Magnell, Esq., and Amy B. Pereira, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST

1. Protest is timely in the absence of evidence that the protester knew or should have
known of the protest basis more than 10 days before the protest was filed.

2. Protest challenging the issuance of a letter of technical direction is sustained, where
the letter directs the contractor to perform work that is out of scope of the underlying
task order.
DECISION

Alliant Solutions, LLC1 (Alliant), of Reston, Virginia, protests, as an improper
modification, the assignment of work to Smartronix, Inc. (Smartronix), of Hollywood,
Maryland, using technical direction letter (TDL) No. 2018-53, on a task order issued to
Smartronix by the General Services Administration (GSA) for the benefit of the Navy
under GSA's Alliant Governmentwide Acquisition Contract (GWAC). The protester
argues that the TDL work falls outside of the scope of Smartronix's task order and that,


1 Alliant is a joint venture originally formed by seven members, including Sabre
Systems, Inc. (Sabre), of Warrington, Pennsylvania. Protester Ltr. to GAO, Mar. 20,
2018, Exh. 1, Alliant Joint Venture & Operating Agreement, at 1. The members may
cooperate with or compete against one another within the joint venture for the right to
submit a quotation through Alliant. Id., Exh. B, Division of Work.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most