B-413981 1 (2017-01-17)

handle is hein.gao/gaobadtbw0001 and id is 1 raw text is: 




         G    A    O                                                   Comptroller General
      Accountabilty * Integrity * Reliability                          of the United States
United States Government Accountability Office  DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                The decision issued on the date below was subject to
                                                    a GAO Protective Order. This redacted version has
                                                    been approved for public release.
         D e c i s i o n                           - .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


         Matter of:   Raytheon Company

         File:        B-413981

         Date:        January 17, 2017

         Michael A. Hordell, Esq., Gary J. Campbell, Esq., G. Matthew Koehl, Esq.,
         Kristopher J. Berr, Esq., and Erin F. Masini, Esq., Pepper Hamilton LLP, for the
         protester.
         Devon E. Hewitt, Esq., Protorae Law PLLC, for Leidos, Inc., the intervenor.
         Judith L. Richardson, Esq., Defense Threat Reduction Agency, for the agency.
         Glenn G. Wolcott, Esq., and Christina Sklarew, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         1. Protest that agency unreasonably evaluated awardee's technical proposal is
         denied where agency reasonably considered awardee's innovative technical
         approach and concluded that it was superior to protester's approach.

         2. Agency reasonably determined that awardee's proposed rates were realistic
         where those rates reflected the awardee's proposed technical approach of
         [redacted].
         DECISION

         Raytheon Company, of Sterling, Virginia, protests the Defense Threat Reduction
         Agency's (DTRA or agency) award of a task order to Leidos, Inc., of Reston,
         Virginia, pursuant to request for proposals (RFP) No. HDTRA1-14-WMD-0058 to
         provide engineering support and vulnerability assessments.' Raytheon asserts that

         1 DTRA is the Department of Defense agency responsible for countering weapons
         of mass destruction (WMD), and the agency states that the DTRA division for which
         this procurement is being conducted (referred to as J9CXA) develops new
         methodologies, processes and technological applications for detecting, locating,
         identifying, physically and functionally characterizing, modeling, and assessing new
         and existing Hard and Deeply Buried Targets (HDBTs) and WMD targets to support
                                                                            (continued...)

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most