        G     A    O                                                 Comptroller General
      Accountabilty * Integrity * Reliability                         of the United States
United States Government Accountability Office  DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548
                                                   The decision issued on the date below was subject to
                                                   a GAO Protective Order. This redacted version has
         Decision Ofbeen approved for public release.




         Matter of: Innovative Test Asset Solutions, LLC

         File:       B-411687; B-411687.2

         Date:       October 2, 2015

         Robert J. Symon, Esq., Aron C. Beezley, Esq., Jennifer F. Brinkley, Esq., and Lisa
         A. Markman, Esq., Bradley Arant Boult Cummings LLP, for the protester.
         Michael F. Mason, Esq., Thomas L. McGovern III, Esq., C. Peter Dungan, Esq.,
         Michael D. McGill, Esq., and Christine Reynolds, Esq., Hogan Lovells US LLP, for
         National Aerospace Solutions, LLC, an intervenor.
         Lt. Col. Mark E. Allen, Maj. Damund E. Williams, Lt. Col. Aaron E. Woodward,
         Gregory B. Porter, Esq., Capt. Brett A. Johnson, and Capt. Andrew S. Herzog,
         Department of the Air Force, for the agency.
         Louis A. Chiarella, Esq., and Nora K. Adkins, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         1. Protest challenging the technical evaluation is sustained where the agency failed
         to reasonably evaluate technical risk in accordance with the terms of the solicitation.

         2. Protest challenging the agency's evaluation of the awardee's past performance
         is denied where the evaluation was reasonable and consistent with the solicitation's
         stated evaluation criteria.

         3. Protest challenging agency's cost realism evaluation is denied where the record
         demonstrates that the agency's conclusions were reasonable.

         4. Protest that agency failed to give adequate consideration to awardee's potential
         organizational conflict of interest (OCI) is denied, where the record shows that the
         agency investigated potential OCIs and reasonably concluded that awardee's plan
         would adequately avoid, neutralize, or mitigate the potential conflicts of interest.
         DECISION

         Innovative Test Asset Solutions, LLC (ITAS), of Tullahoma, Tennessee, protests the
         award of a contract to National Aerospace Solutions, LLC (NAS), of Reston,
         Virginia, under request for proposals (RFP) No. FA9101-13-R-01 00, issued by the

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most