B-411306,B-411306.3,B-411306.4 1 (2015-07-08)

handle is hein.gao/gaobadrga0001 and id is 1 raw text is: 




         G     A    O                                                    Comptroller General
       Accountabilty * Integrity * Reliability                            of the United States
United States Government Accountability Office          DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.
         D  e c i s i o n                            L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


         Matter of:   Coulson Aviation (USA), Inc.

         File:        B-411306; B-411306.3; B-411306.4

         Date:        July 8, 2015

         Jonathan D. Shaffer, Esq., and Mary Pat Buckenmeyer, Esq., Smith Pachter
         McWhorter PLC, for the protester.
         Melissa D. McClellan, Esq., Department of Agriculture, for the agency.
         Evan D. Wesser, Esq., and Jonathan L. Kang, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         1. In a procurement for airtanker services for wildfire firefighting support, the
         protester is not an interested party to challenge a solicitation requirement to submit
         proof of safety certification as being unduly restrictive of competition where the
         protester did not have the safety certifications even after the extended period of
         time requested by the protester has elapsed.

         2. Protest challenging the requirement for a pre-award inspection is dismissed
         where the protester suffered no competitive prejudice because it otherwise was
         ineligible for award.

         3. Protest challenging the amount of time afforded to offerors to respond to the
         solicitation is denied where the record shows that the agency provided reasonable
         advance notice to offerors of the agency's requirements and afforded offerors a
         reasonable opportunity to respond to the solicitation.
         DECISION

         Coulson Aviation (USA) Inc., of Port Alberni, British Columbia, Canada, challenges
         the terms of request for proposals (RFP) No. AG-024B-S-1 5-9003, which was
         issued by the Department of Agriculture, Forest Service for next generation
         (NextGen) large airtanker services for wildfire firefighting support.' Coulson argues

         1 This procurement is referred to as the NextGen 2.0 procurement because it is the
         follow-on procurement to the previous NextGen 1.0 procurement. The Forest
                                                                              (continued...)

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most