B-408847.2 1 (2014-01-17)

handle is hein.gao/gaobadqbv0001 and id is 1 raw text is: 




          G     A    O                                                   Comptroller General
Ac       ;taa bity I integrilty I Reiiabikty                            of the United States
  United States Government Accountability Office    DOCUMENT FOR PUBLIC RELEASE
  Washington, DC 20548                                The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.
           D  e c i s i o n                          L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


           Matter of:  Environmental Systems Research Institute, Inc.

           File:       B-408847.2

           Date:       January 17, 2014

           Christopher C. Bouquet, Esq., and Wayne A. Keup, Esq., for the protester.
           Daniel F. Edwards, Esq., Daniel P. Broderick, Esq., Christian F. Henel, Esq., and
           Lawrence M. Prosen, Esq., Thompson Hine LLP, for URS Group, Inc.,
           an intervenor.
           Sherry Kinland Kaswell, Esq., and Sarah Zaffina, Esq., Department of the Interior,
           for the agency.
           Paul E. Jordan, Esq., and David A. Ashen, Esq., Office of the General Counsel,
           GAO, participated in the preparation of the decision.
           DIGEST

           Protest against rejection of proposal as unacceptable is denied where solicitation
           required offerors to provide fixed prices for all proposed software, and agency
           reasonably concluded that protester's submission of partial pricing information and
           reliance on expiring enterprise license agreement did not meet requirement for
           submission of fixed prices.
           DECISION

           Environmental Systems Research Institute, Inc. (Esri), of Redlands, California,
           protests the Department of the Interior (DOI), Bureau of Land Management's (BLM)
           award of a contract to URS Group, Inc., of San Antonio, Texas, under request for
           proposals (RFP) No. 783465, for development and implementation of the
           Geospatial Publication Module (GPM), a web-based software application. Esri
           challenges the evaluation of its technical proposal and price.

           We deny the protest.

           BACKGROUND

           The RFP contemplated issuance of a fixed-price, indefinite-delivery/indefinite-
           quantity (IDIQ) contract for web-based geospatial services related to the GPM, for a
           base year with four 1-year options, with total task orders not to exceed $15 million

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most