B-403771.2 1 (2011-02-10)

handle is hein.gao/gaobadoxm0001 and id is 1 raw text is: 


   i

                         G  A  0Comptroller General
.    Ln Accountability * Integrity * Reliability                       of the United States
United States Government Accountability Office         DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
                                                      approved for public release.
                                                    L - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - --.

           Decision

           Matter of:   Genco Infrastructure Solutions, Inc.

           File:       B-403771.2

           Date:       February 10, 2011

           Wayne A. Keup, Esq., for the protester.
           William K. Walker, Esq., Walker Reausaw, for Olgoonik Environmental Services, an
           intervenor.
           Timothy J. Ryan, Esq., Department of Defense, for the agency.
           Mary G. Curcio, Esq., and David A. Ashen, Esq., Office of the General Counsel, GAO,
           participated in the preparation of the decision.
           DIGEST

           1. Procuring agency may base past performance evaluation of offeror on the past
           performance of a subcontractor that will be performing a substantial portion of the
           contract.

           2. Protest that awardee's lack of experience should have resulted in a rating of less
           than acceptable under management capability factor is denied where solicitation
           provided for evaluation under that factor of offeror's proposed approach to
           performance rather than its prior experience.

           3. Protest that agency improperly considered HubZone evaluation preference is
           untimely where solicitation provided for preference and protest was not filed until
           after the initial closing date for the receipt of proposals.
           DECISION

           Genco Infrastructure Solutions, Inc., of Pittsburgh, Pennsylvania, protests the award
           of a contract to Olgoonik Environmental Services (OES), of Wainwright, Alaska,
           under solicitation No. SP3300-09-R-0035, issued by the Department of Defense,
           Defense Logistics Agency, for warehouse and distribution support services. Genco
           challenges the evaluation of proposals.

           We deny the protest.

           The solicitation provided for award to the offeror whose proposal was most
           advantageous based on price and the following six non-price factors (in descending

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most