B-406100,B-406100.2 1 (2012-02-08)

handle is hein.gao/gaobadopn0001 and id is 1 raw text is: 



I      QA                                                                Comptroller General
        Accountability * Integrity * Reliability                          of the United States
United States Government Accountability Office     DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.
                                                      L  - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - i
          Decision

          Matter of:   McTech Corporation

          File:        B-4061 00; B-406100.2

          Date:        February 8, 2012

          Hilary S. Cairnie, Esq., Udyogi A. Hangawatte, Esq., and Andrene Smith, Esq.,
          Baker & Hostetler LLP, for the protester.
          Charles L. Webster III, Esq., Department of the Army, for the agency.
          Katherine I. Riback, Esq., and James A. Spangenberg, Esq., Office of the General
          Counsel, GAO, participated in the preparation of the decision.
          DIGEST

          1. Agency reasonably concluded that the protester had an organizational conflict of
          interest and properly eliminated it from the competition under a solicitation for the
          award of a construction contract, where the agency found that the close relationship
          between the protester and the designer of the construction project constituted an
          apparent conflict of interest that created the appearance of an unfair competitive
          advantage.

          2. Protester's contention that information not considered by the contracting officer in
          the initial determination that the protester had an organizational conflict of interest
          (OCI) cannot be considered by GAO in resolving a protest challenging this
          determination is denied because an agency may provide further information and
          analysis regarding the existence of an OCI at any time during the course of a
          protest, and GAO will consider such information in determining whether the
          contracting officer's OCI determination is reasonable.
          DECISION

          McTech Corporation, of Cleveland, Ohio, protests its exclusion from the competition
          under request for proposals (RFP) No. W9126G-1 1 -R-01 28, issued by the
          Department of the Army, U.S. Army Corps of Engineers, for the construction of
          dormitories, a conference center, and related improvements at the Department of
          Homeland Security's (DHS) Training Center, located in Harpers Ferry, West Virginia.
          The agency excluded McTech from the competition based on the contracting
          officer's (CO) determination that McTech had an organizational conflict of interest
          (OCI). McTech contends that the CO's determination was unreasonable.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most