B-220067 1 (1986-01-22)

handle is hein.gao/gaobadmdp0001 and id is 1 raw text is: - - II ICe l


                         THE COMPTROLLER OENEAL
 OKCISION                OP . o THE UNITSO STATES
                         WAS HINGTO N. D.C. 20548




 FILE:     B-220067            DATE: January 22, 1986

 MATTER OF:     Western Alaska Contractors


 DIGEST:
    Where contract was awarded to low bidder which
    alleged mistake in its bid before award and
    parties agreed that contractor could pursue
    mistake claim, contract should be reformed to
    increase price in amount equal to an
    electrical subcontractor's quotation, because
    bid workpapers contain clear and convincing
    evidence that electrical subcontractor's
    quotation was mistakenly omitted from bid.
    Rowever, contract should not be reformed to
    reflect claimed markup on electrical
    subcontractor's quotation, because bid
    workpapers do not show any markup or
    oercentaqe used to compute markup for
    subcontract work nor do workpapers show any
    Pattern of applying markup on individual cost
    items.

    Western Alaska Contractors requests our review of the
Army Corps of Engineers' denial of its preaward request to
correct a mistake in its low bid submitted in response to
invitation for bids No. DACA85-85-B-0036 issued by the
Alaska District of the Corps for construction of miscella-
neous mechanical and electrical maintenance and repair
projects at Shemya Air Porce Base. Notwithstandinq the
alleged mistake, Western Alaska was awarded the contract at
its uncorrected bid price of $2,455,000. The parties
agreed, however, that Western Alaska could present its pre-
award claim for bid correction to our Office for resolution.

     We find that Western Alaska's contract should be
reformed to allow upward correction representing the amount
of a subcontractor quotation which was inadvertently omitted
by Western Alaska from its bid. However, Western Alaska's
request for correction in an additional amount representing
markuo on the omitted subcontractor quotation is denied.

     The basic facts are not in dispute. Six bids were
received bv the Corps in resoonse to the invitation, ranging






                        O    4LL~

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most