B-201642.2 1 (1983-04-22)

handle is hein.gao/gaobadlas0001 and id is 1 raw text is: 
                                                     '  /   / 0

                                THE COMPTROLLER GENERAL
        DECISION                0 ? ,. OF THE UNITED STATE8
                                WASHINGTON, D.C. 20548




       FILE:B-201642.2                DATE:   April 22, 1983

       MATTER OF:     Four-Phase Systems, Inc.--
                      request for reconsideration

        DIGEST:



    Earlier decision denied protest that agency was
    procuring computing capacity in excess of its minimum
    needs because agency provided studies justifying
    needs and protester did not show that basis for needs
    was unreasonable. Subsequent GAO audit found that
    studies were erroneously performed and reached
    incorrect conclusions. Request for reconsideration
    based on that information is sustained, and prior
    decision is modified accordingly.

    Four-Phase Systems, Inc. (Four-Phase), requests
reconsideration of our decision in Four-Phase Systems, Inc.,
B-201642, July 22, 1981, 81-2 CPD 56, in which we denied
Four-Phase's protest under request for proposals (RFP)
No. DTFA01-80-R-31147 for computer systems for 10 automatic
data processing centers issued by the Federal Aviation
Administration (FAA), Department of Transportation.

    In that decision, we considered Four-Phase's allegations
that the RFP was ambiguous, that the requirements stated
therein were in excess of the FAA's minimum needs, and that
it did not include all costs that should be evaluated. We
denied the protest on all grounds. Concerning the ground
that is relevant to this request for reconsideration, we
found that Four-Phase had not met its burden of showing that
the FAA's justification of its minimum needs was without a
reasonable basis. A contract was awarded to Small Business
Systems, Inc. (SBS), on April 5, 1982.
    On April 20, 1982, GAO issued a report titled
Examination of the Federal Aviation Administration's Plan
for the National Airspace System--Interim Report (AFMD-
82-66), in which we examined, among other things, the FAA's
justification and handling of the procurement that had been
the subject of our July 22, 1981, decision. In that report,
we found that the FAA had procured computing power far in
excess of its needs. We recommended that FAA cancel the
contract awarded_ toSBS .

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most