                            THE  COMPTROLLER GENERAL
    DECISION      *         OF  THE   UNITED STATES
                            WASHINGTON, D.C. 20548



    FILE:  B-194610               DATE:  April 1, 1980

    MATTER  OF:     Andy Electric Company


    DIGEST:


    1.  Where contracting officer did not know that
        Government estimate was erroneous when bidder
        was requested to verify low bid based on esti-
        mate and other bids received, verification
        ;request was sufficient.

     2. Award to low bidder after bid verification was
        not unconscionable, notwithstanding second low
        bid was about 130 percent more than low bid,
        since it is not established that contracting
        officer knew that Government was essentially
        'getting something for nothing.'


        Andy  Electric Company (Andy) has requested that
    contract No. DACA21-77-C-0062 awarded February 18,
    1977, for alteration of various fire alarm systems
/9, at Hunter Army Airfield be increased by $34,642 to
    $61,221.20 because of an error in bid alleged 5 months
    after completion of the work and before final settlement
    of the contract.

         Prior to award of the contract, Andy was advised
    that the Government cost estimate for the work was
    $37,201 and that the two other bids received were
    $61,223 and $81,565.  Andy consequently was requested
    to verify its low bid of $26,579.20. Andy verified
    the bid.  As a result of Andy's present claim for
    an increase in the contract price, the Government
    estimate was reviewed and has been revised upward
    to $53,508.  Andy contends that in verifying the bid
    it relied upon the closeness of the then-reported
    Government estimate and discounted the significance
    of the higher bids.  Andy states that, if it had been
    presented with a correct Government cost estimate,
    it would have made a thorough examination of all the
    bid computations and discovered the error prior to
    award.  Because the erroneous Government estimate
    allegedly was responsible for the verification, Andy

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most