About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

B-193715 1 (1979-04-02)

handle is hein.gao/gaobadhbc0001 and id is 1 raw text is: 




                              THE  COMPTROLLER GENERAL
 Insicm          .            OF   THE    UNITED'STATES
                              WASHINGTON, D.C. 20549




 FILE: B-193715                     DATE:    April 2, 1979

 MATTER   OF:   Paragon Mechanical


 DIGEST:

   tRequest-b by=<e ta : for contract modification to remedy
     alleged clerical error in bid price preparation can not be
     allowed where mistake was unilateral, there was no actual
     notice, and awardee's lump-sum bid was higher than Govern-
     ment estimated project cost and less than one percent lower
     than next lowest bid, thereby precluding possibility that
     mistake was so apparent as to warrant charging contracting
     officer with constructive notice.

     Paragon Mechanical (Paragon) requests reformation of contract
No. GS-06B-71060 due to a mistake in bid first alleged after award.
The contract, awarded by Region 6 of the General Services Adminis-
tration (GSA), is for renovations in the Federal Building in Kansas
City, Missouri.

     The invitation for bids (IFB) was issued by GSA on July 11,
1978, for base work consisting of modernizing 23 rest rooms. The
IFB also called for a separate price as Alternate A, for renovation
work in the FSS Swing Room. At bid opening on August 10, 1978,
Paragon was found to have submitted the low bid of $569,460 for
the base contract work, plus $56,250 for Alternate A (total $625,710),
The next low bid, submitted by Mid-Western Construction Co., was
$578,335 for the base contract work and $49,100 for Alternate A
(total $627,435).  GSA had estimated the cost of the work at $521,390
for the base contract work and $38,300 for Alternate A (total $559,690).

     Paragon was awarded the contract, including Alternate A, on
September 13, 1978, for $625,710. Paragon commenced work on October 9,
1978.  By letter dated October 31, 1978, Paragon first advised GSA
that it had discovered a clerical error involving the incorrect
carry-forward of subtotals in its bid calculations which caused an
understatement of $46,600. Paragon requested price adjustment in
this amount, pursuant to the Federal Procurement Regulations (FPR)
§ 1-2.406-4.  This request was denied-by the contracting officer by
letter dated November 20, 1978.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most