B-184194 1 (1976-07-19)

handle is hein.gao/gaobadcwo0001 and id is 1 raw text is:                              THE  COMPTROLLER GENERAL
DECISION         .           OF   THE    UNITED      STATES
                             WASHINGTON. D.C. 20548




FILE:   B-184194                    OATE:   July 19, 1976

MATTER OF: Environmental Protection Agency                     q
                Request for Modification of GAO Recommendation

DIGEST:

1.  GAO Bid Protest Procedures provide that requests for
    reconsideration must be filed within 10 working days
    by appropriate interested party or agency. However,
    considering agency's request that modification of
    recommendation in GAO decision be allowed--due to
    changing circumstances in procurement--has also
    been recognized as appropriate and is not incon-
    sistent with Bid Protest Procedures. To decline
    to consider such information could jeopardize best
    interests of Government.

2.  Though it is contended that contracting agency's
    procrastination in responding to protest has pre-
    vented protester from obtaining equitable and just
    result, record does not support allegation that all
    delays were caused by agency, but rather shows that
    substantial delays in protest proceedings are directly
    attributable to protester's actions.

3.  Some changes in request for proposals (RFP) can be
    made appropriately by amendment, but substantial
    changes may justify canceling RFP and issuing new,
    revised RFP.  While several reasons offered by agency
    for canceling RFP are subject to question, others indi-
    cate that certain amendments to RFP are appropriate and
    necessary.  Amendments may revise RFP's terms to extent
    that, as agency claims, it would become preferable to
    cancel and resolicit.

4.  Contention that agency issued three RFP's to circumvent
    effect of protest pending under separate RFP involves
    subjective motives of agency officials which cannot be
    conclusively'established on written record. No provi-
    sion of procurement law specifically prohibits concurrent
    procurement of work similar to work being sought under
    protested solicitation.  Moreover, three additional RFP's



                             - 1 -        PUBLISHED DECISiON
                                          55 Com2. Gen....9....

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most