B-404721,B-404721.2 1 (2011-04-19)

handle is hein.gao/gaobadbun0001 and id is 1 raw text is: 




         G     A    0                                                 Comptroller General
       Accountability * Integrity * Reliability                       of the United States
United States Government Accountability Office    DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to a
                                                     GAO Protective Order. This redacted version has been
                                                     approved for public release.

          Decision

          Matter of:  ERC, Inc.

          File:       B-404721; B-404721.2

          Date:       April 19, 2011

          Robert J. Symon, Esq., and Daniel P. Golden, Esq., Bradley Arant Boult Cummings
          LLP, for the protester.
          J. Andrew Watson III, Esq., Stephen D. Davis II, Esq., and L. Justin Burney, Esq.,
          Maynard Cooper & Gale, P.C., for Al Signal Research, Inc., an intervenor.
          Tina Marie Pixler, Esq., and Dennis J. Gearin, Esq., Department of the Army, for the
          agency.
          Linda C. Glass, Esq., and Sharon L. Larkin, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          Protest challenging cost realism analysis is denied, where agency performed a
          comprehensive analysis of all major cost elements and relied on reviews and
          recommendations  by the Defense Contract Audit Agency to reasonably determine
          that proposed costs were realistic for the work to be performed.
          DECISION

          ERC, Inc., of Huntsville, Alabama, protests the award of a contract to Al Signal
          Research, Inc. (ASRI), also of Huntsville, under request for proposals (RFP)
          No. W31P4Q-09-R-0008, issued by the Department of the Army, U.S. Army Material
          Command,  for support services for the Redstone Test Center's Environmental and
          Component  Test Directorate. ERC, the incumbent, challenges the agency's cost
          realism evaluation.

          We deny the protest.

          BACKGROUND

          The Army issued the RFP on March 20, 2009, as a competitive small business
          set-aside. RFP at 2. The RFP provided for award of a cost-plus-fixed-fee
          indefinite-delivery/indefinite-quantity contract for a 12-month ordering period with
          four successive 12-month ordering periods, for a total performance period of
          60 months. Id. The RFP provided that award of the contract would be made on a

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most