A     ,   GA       O                                                  Comptroller General
        countabiity * Integrity * Reliability                          of the United States
 United States Government Accountability Office
 Washington, DC 20548

              D  ..
          Decision


          Matter  of: JND  Thomas  Company, Inc.

          File:       B-402240

          Date:       January 28, 2010

          William L. Bruckner, Esq., Bruckner & Walker, LLP, for the protester.
          Annette B. Kuz, Esq., U.S. Army Corps of Engineers, for the agency.
          Paul E. Jordan, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          Protest that intended awardee's bid is impermissibly unbalanced--due to alleged
          overstated prices for excavation/dredging line items and understated prices for
          related re-handling of material items--is denied where agency conducted analysis of
          pricing and concluded that there was no significant price risk in accepting bid.
          DECISION

          JND Thomas  Company,  Inc., Riverdale, California, protests the award of a contract
          to CJW Construction, Inc., of Santa Ana, California, under invitation for bids (IFB)
          No. W912PL-09-B-0005, issued by the U.S. Army Corps of Engineers for excavation
          and dredging work at the Marine Corps Base, Camp Pendleton, California. JND
          asserts that CJW's bid should have been rejected as unbalanced.

          We deny the protest.

          The purpose of the procurement is to increase the surface water storage capacity of
          Lake O'Neill at Camp Pendleton by performing maintenance dredging and related
          rehabilitation of existing (dry) recharge pond Nos. 4-7 through excavation,
          installation of spillway culverts, and construction of a levee around pond Nos. 6
          and 7. Under the terms of the IFB, the contractor would be allowed 600 days to
          complete the project. IFB § 00800 at 2. The IFB called for lump-sum bids for
          mobilization/demobilization, clear/grub pond Nos. 4-7, storm water pollution
          prevention plan development/compliance, and temporary water delivery, and unit
          price bids for excavation/re-handling of dry excavated material from pond Nos. 4-7
          (estimated 257,000 cubic yards (CY)), levee construction, culvert installation, riprap
          placement, and dredging/re-handling of wet dredge material (estimated 361,000 CY)

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most