GAO-02-1069R 1 (2002-09-24)

handle is hein.gao/gaobaamby0001 and id is 1 raw text is: 

   £


       Accountability * Integrity * Reliability
United States General Accounting Office
Washington, DC 20548



         September 24, 2002

         The Honorable Constance A. Morella
         Chairwoman
         Subcommittee on the District of Columbia
         Committee on Government Reform
         House of Representatives

         Subject: District of Columbia: Status of Construction of the Convention Center

         Dear Madam Chairwoman:

         You asked us to provide periodic briefings on the status of the construction of the
         new convention center in Washington, D.C. The convention center is being
         constructed in accordance with the Washington Convention Center Authority Act of
         1994, which authorizes the Washington Convention Center Authority (WCCA) to
         construct, maintain, and operate a new convention center while continuing to
         maintain and operate the existing convention center.

         As agreed with your office, we reviewed information related to the status of the
         convention center construction, costs, and financing as of June 2002, the most recent
         information available at the time of our review.

         Specifically, our objectives were to provide information on (1) issues related to the
         Revised Guaranteed Maximum Price agreement (RGMP)1 set in January 2002, (2) the
         status of construction and significant construction issues that could delay completion
         of the project, (3) whether the January 2002 estimated total project cost2 of $799.5
         million has changed, and, if so, the causes and nature of the changes, and (4) whether
         WCCA's funding appears to be sufficient to cover the current estimated total project
         cost.

         In order to meet these objectives, we reviewed the RGMP, held discussions with and
         obtained information from WCCA officials and the DC City Council's oversight
         contractor for the project, reviewed the construction manager's (CM) and WCCA's
         monthly progress reports and WCCA's financing plan, visited the construction site,
         and considered the results of our prior work, which were most recently reported to

         'The RGMP is intended to represent the final construction price negotiated for hard costs between the
         construction manager and WCCA.
         2 WCCA established the $799.5 million total project cost estimate in January 2002.


GAO-02-1069R Status of New Convention Center

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most