About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

3 Pub. Cont. Newsl. 1 (1967-1968)

handle is hein.journals/procurlw3 and id is 1 raw text is: 







SECTION OF
PUBLIC CONTRACT LAW
AMERICAN BAR
ASSOCIATION

     Vol. 3, No. 1, Dec. 1967


FEDERAL STATE & LOCAL GOVERNMENT CONTRACTS


Charlotte P. Murphy, Editor, P.O. Box 7783, Washington, D.C. 20014


      NEW CHANGES, DIFFERING SITE
 CONDITIONS, AND SUSPENSION OF WORK
        CLAUSES, ISSUED BY G.S.A. FOR
          CONSTRUCTION CONTRACTS

Culminating three years of effort, G.S.A., on November 28,
1967, published in the Federal Register the new mandatory
Changes, Differing Site Conditions, and Suspension Of
Work clauses for use in Standard Form 23-A for fixed-price
construction contracts (FPR § § 1-7.601-2, 1-7.601-3, and
1-7.601-4).
   Although many changes have been made in the language
of the new clauses since the initial drafts were written, the
basic provisions contained in the first draft have been
retained (See Public Contract Newsletter, Vol. 1, No. 3,
July 1966). The Section actively participated in discussions
with G.S.A. and the Government Interagency Working
Group in an effort to improve and clarify the clauses.
   The major revisions effected by the new clauses include
the elimination of the Rice Doctrine with respect to the
effects of changes on portions of the work not specifically
changed; a similar provision with respect to Differing Site
Conditions (the new title of the old Changed Conditions
clause); and a mandatory requirement that the Suspension
Of Work clause be used in all contracts.
   At the suggestion of the Section, the new clauses were
revised to delete all references to the Disputes clause to
avoid any change in the existing jurisdiction of the boards of
contract appeals and the Court of Claims.
   The new clauses retain the standard of unreasonable
delay in the Suspension clause, but in accordance with
the comments of the Section, this standard was eliminated
from the new Changes, and Differing Site Conditions
clauses.
   Despite unanimous objection by industry and the Section,
the new clauses include onerous notice requirements, with
inadequate provision for waiver. In an appendix published
with the new clauses, ambiguities and a possible conflict with
the language of the new clauses are introduced with regard to
whether delay costs incurred prior to the issuance of changes
are to be paid under the Changes clause or the Suspension
of Work clause.
   Despite these defects, the Section, on September 18,
1967, recommended that the revised clauses be adopted,
since the clauses represent a significant advance in construc-
tion contract arrangements, but urged that efforts continue
in the task of improving and refining the clauses.
   The new clauses become mandatory on February 1,


1968, but may be used before that date. Nothing in the new
clauses, or the regulations adopting them, would preclude
the parties to an existing contract from executing a supple-
mental agreement to substitute the revised clauses.

5TH CIRCUIT REFUSES GOVT. RIGHT TO SET
    OFF CONTRACTOR'S TAXES AGAINST
                 SURETY'S CLAIM
In Trinity Universal ins. Co. & 1st National Bank (Dallas) v.
U.S., decided Sept. 12, 1967 by the Court of Appeals for the
5th Circuit, the issue was whether, when a Miller Act surety
completes a defaulted contract pursuant to its performance
bond, (and expends more than the full contract price), the
Government may set off taxes owed by the contractor
against the surety's claim to the fund retained by the
Government to insure performance.
    The surety's claim was rejected by the district court on
authority of U.S. v.Munsey Trust Co., 332 U.S. 234 (1947).
The rights of the surety in that case were those of a subrogee
of the contractor, with the person paying the laborers and
materialmen becoming a creditor of the Government insofar
as the retained funds are concerned. See, Pearlman v. Reliance
Ins. Co., 371 U.S. 132, 141.
    In reversing the lower court, the Court of Appeals
specifically rejected the opposite view expressed in
Standard Accident Ins. Co. v. U.S., 97 F. Supp. 829 (Ct. Cls.
1951). The Court held that: the surety should not be worse
off because it undertook to finish the job. The performance
bond is to assure that the Government has a completed
project for the agreed contract price. The obligation may be
performed either in kind or in money. Performance results
equally when the surety completes the contract or when the
surety pays the Government any damage which the
Government incurs in completing the job. In either event,
the surety is entitled to have the full contract price applied
to the performance of the contract.
    At presstime, the Government had not yet announced
whether it would file a petition for certiorari.

              FUTURE EVENTS PREVIEW
    April 5, 6, 1968 - Two day National Institute to be
 sponsored by our Section at the Mayflower Hotel in
 Washington, D.C.
    August 4- 6, 1968 - PCS/ABA Annual Meeting in
 Philadelphia. The Section will sponsor three half day sessions,
 its traditional luncheon, and two Council meetings-all meet-
 ings are to be held at the new Convention Center.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Short-term subscription options include 24 hours, 48 hours, or 1 week to HeinOnline.

Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most