B-299931 1 (2007-10-10)

handle is hein.gao/gaocrptauhk0001 and id is 1 raw text is: 




A         G    A    O                                                   Comptroller General
.       Accountability * Integrity * Reliability                        of the United States
United States Government Accountability Office      DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
                                                      approved for public release.

          Decision

          Matter of: GlassLock, Inc.

          File:        B-299931; B-299931.2

          Date:        October 10, 2007

          Robert S. Brams, Esq., and Elizabeth M. Gill, Esq., Patton Boggs LLP, for the
          protester.
          Jonathan S. Baker, Esq., Environmental Protection Agency, for the agency.
          Katherine I. Riback, Esq., and James A. Spangenberg, Esq., Office of General
          Counsel, GAO, participated in the preparation of the decision.
          DIGEST

          1. Under a solicitation for competitive quotations issued under the Federal Supply
          Schedule program that only provided for vendors to submit prior experience/past
          performance references for the past 5 years, an agency improperly considered and
          awarded strengths, based on information provided by the successful vendor with its
          quotation, for projects that were completed more than 5 years ago.

          2. Agency failed to evaluate quotations reasonably or in accordance with the
          solicitation where strengths relating to the successful vendor's experience and past
          performance were assigned under the project plan/schedule technical factor, which
          did not encompass evaluation of the vendor's experience and past performance, and
          where the solicitation contained a separate evaluation factor for experience/past
          performance under which the successful vendor received consideration for its
          experience/past performance.

          3. Under solicitation for competitive quotations issued under the Federal Supply
          Schedule program that provided for a tradeoff analysis with technical factors being
          more important than price, agency improperly based issuance of an order on the
          lowest-priced, technically acceptable quotation.
          DECISION

          GlassLock, Inc. protests the award of a task order to Commercial Window Shield
          (CWS) under request for quotations (RFQ) No. RFQ-DC-07-00168, issued by the
          Environmental Protection Agency (EPA) for the procurement and installation of
          window retrofits for window glass fragment retention in 15 EPA facilities in the

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most