B-298662 1 (2006-11-15)

handle is hein.gao/gaocrptasrl0001 and id is 1 raw text is: 




A         G    A    O                                                  Comptroller General
.       Accountability * Integrity * Reliability                       of the United States
United States Government Accountability Office
Washington, DC 20548                                   DOCUMENT FOR PUBLIC RELEASE
                                                      The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
          Decision                                  .approved for public release.



          Matter of: Advanced Federal Services Corp.

          File:        B-298662

          Date:        November 15, 2006

          Howell Roger Riggs, Jr., Esq., Patrick 0. Miller, Esq., and David H. Stem, Jr., Esq.,
          Dick, Riggs, Miller & Stem, LLP for the protester.
          Ronald K. Henry, Esq., John L. Bowles, Esq., and Kevin S. Donohue, Esq., Kaye
          Scholer, LLP, for Eastek, Inc., an intervenor.
          Jeffrey I. Kessler, Esq. and Janet K. Baker, Esq., Army Materiel Command, for the
          agency.
          Jonathan L. Kang, Esq., and Glenn G. Wolcott, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Protest challenging agency's evaluation of offerors' proposals and source selection
          decision is denied where agency's determinations were reasonable and consistent
          with the solicitation.
          DECISION

          Advanced Federal Services Corp. (AFS) protests the award of a contract to
          Eastek, Inc. under request for proposals (RFP) No. W9128Z-06-R-0001, issued by the
          Department of the Army Communications-Electronics Life Cycle Management
          Command for business administrative support services (BASS). The protester
          contends that the agency unreasonably evaluated offerors' technical proposals and
          past performance and made an improper source selection decision.

          We deny the protest.

          BACKGROUND

          The RFP sought proposals to provide BASS requirements for the Army Information
          Systems Engineering Command, Army Communications Security Logistics Activity,
          and the Communications-Electronics Life Cycle Management Command Acquisition
          Center Southwest. Offerors were required to propose BASS requirements for these
          facilities, including administrative support, shipping and receiving, logistics, system

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most