A         G    A    O                                                   Comptroller General
.       Accountability * Integrity * Reliability                        of the United States
United States Government Accountability Office     DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
                                                      approved for public release.

          Decision


          Matter of: Miramar Construction, Inc.

          File:        B-298609

          Date:        October 31, 2006

          Alan Dickson, Esq., Paul C. Burkholder, Esq., and Tammy Hopkins, Esq., Epstein
          Becker & Green, for the protester.
          Kerry S. Curtis, Esq., U.S. Army Corps of Engineers, for the agency.
          Tania Calhoun, Esq., and Christine S. Melody, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Contracting agency's determination to permit bidder to upwardly correct its
          apparent low bid lacks a reasonable basis where bidder's explanation for alleged
          mistake is illogical and raises questions as to whether a mistake occurred, and where
          agency's determination fails to address these questions and relies on
          mischaracterizations of the bidder's explanation.
          DECISION

          Miramar Construction, Inc. protests the proposed award of a contract to ERS-JV
          under invitation for bids (IFB) No. W912PL-06-B-0008, issued by the U.S. Army Corps
          of Engineers, Los Angeles District, for the removal and replacement of sewer
          lagoons in wastewater treatment facilities at the Yuma Proving Ground in Arizona.
          Miramar primarily argues that the Army improperly permitted ERS-JV to make an
          upward correction to its apparent low bid.

          We sustain the protest.

          The Army issued the solicitation on May 15, 2006 as a competitive section 8(a)
          procurement.' Bidders were required to provide a separate lump sum price for each

          1 Section 8(a) of the Small Business Act authorizes the Small Business
          Administration to contract with other government agencies and to arrange for the
          performance of those contracts via subcontracts awarded to socially and
          economically disadvantaged small businesses. 15 U.S.C. § 637(a) (2000).

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most