B-297219 1 (2005-12-05)

handle is hein.gao/gaocrptaqzn0001 and id is 1 raw text is: 




A         G    A    O                                                 Comptroller General
.       Accountability * Integrity * Reliability                       of the United States
United States Government Accountability Office
Washington, DC 20548



          Decision


          Matter of: Charter Environmental, Inc.

          File:        B-297219

          Date:        December 5, 2005

          Daniel J. Kelly, Esq., and Gary J. Campbell, Esq., Gadsby Hannah, for the protester.
          Azine Farzami, Esq., Department of Agriculture, for the agency.
          John L. Formica, Esq., and James A. Spangenberg, Esq., Office of the General
          Counsel, GAO, participated in the preparation of the decision.
          DIGEST

          1. Contracting agency unreasonably determined that apparent low bidder on
          invitation for bids for the stabilization and removal of mine waste met the
          solicitation's definitive responsibility criterion requiring that the awardee have
          completed three similar projects, where the agency only considered the experience
          of what is apparently the low bidder's parent company, even though the record does
          not contain a commitment by the parent company to the low bidder's successful
          performance of the work.

          2. Bid cannot be rejected as nonresponsive on the basis that the bid did not include
          completed standard representations and certifications or the bidder had not yet
          registered in the Central Contractor Registration.
          DECISION

          Charter Environmental, Inc. protests the proposed award of a contract to ECI
          Northeast, LLC, under invitation for bids (IFB) No NEAT-05-190, issued by the Forest
          Service, Department of Agriculture, for restoration of the Ore Hill Mine Site in New
          Hampshire. Charter argues that ECI Northeast's bid should have been rejected as
          nonresponsive, and that ECI Northeast does not meet the IFB's definitive
          responsibility criteria and is thus ineligible for award.

          We sustain the protest in part and deny it in part.

          The IFB provides for the award of a fixed-price contract for the mine restoration
          services, which include, for example, the removal and stabilization of mine waste.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most