B-294242 1 (2004-08-24)

handle is hein.gao/gaocrptapnz0001 and id is 1 raw text is: 




         G     A    0                                                 Comptroller General
             SIntegrity Reliability                                   of the United States
 ~ccountabthty Inert Rea iy
United States General Accounting Office
Washington, DC 20548




          Decision


          Matter of: Mindleaf Technologies, Inc.

          File:       B-294242, B-294242.2

          Date:       August 24, 2004

          Paresh K. Shah for the protester.
          Clarence D. Long III, Esq., and Capt. David W. Armstrong, Department of the Air
          Force, for the agency.
          Paul F. Khoury, Esq., and William J. Grimaldi, Esq., Wiley Rein & Fielding, for KMR,
          LLC, an intervenor.
          Matthew T. Crosby and James A. Spangenberg, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Agency reasonably determined that awardee's proposal price was not unrealistically
          low where awardee's price was in line with the prices of two other competitive
          proposals.
          DECISION

          Mindleaf Technologies, Inc. protests the award of a contract to KMR, LLC under
          request for proposals FA2823-04-R-0009, issued by the Department of the Air Force
          for operation of central appointments and referral centers for healthcare services at
          Eglin Air Force Base and Hurlburt Field, Florida. Mindleaf challenges the
          reasonableness of the agency's price analysis and performance risk determinations,
          and alleges that it suffered a competitive disadvantage due to disclosure of the firm's
          pricing information.

          We deny the protest.

          On August 1, 2003, the Air Force issued a request for quotations (RFQ) for
          centralized appointment and referral services (CA/RS) for military healthcare
          facilities at Eglin Air Force Base and Hurlburt Field, Florida. The RFQ, issued as a
          small business set aside, contemplated the award of a fixed-price contract to a
          Federal Supply Schedule vendor in accordance with Federal Acquisition Regulation
          (FAR) Subpart 8.4. The selected vendor was to operate a number of call centers and

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most