B-289401 1 (2002-02-20)

handle is hein.gao/gaocrptaoda0001 and id is 1 raw text is: 




         G     A     0                                                Comptroller General
             SIntegrity Reliability                                    of the United States
 ~ccountabthty Inert Rea iy
United States General Accounting Office                DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to a
                                                     GAO Protective Order. This redacted version has been
                                                     approved for public release.

          Decision

          Matter of: MPRI, Inc.

          File:       B-289401

          Date:       February 20, 2002

          Harvey Sherzer, Esq., Scott Arnold, Esq., Joe R. Reeder, Esq., and Neil E. Richman,
          Esq., Greenberg Traurig, for the protester.
          Lee P. Curtis, Esq., and Suzette W. Derrevere, Esq., Perkins Coie, and Terrence
          Murphy, Esq., Patrick H. O'Donnell, Esq., and Mary Elizabeth Anderson, Esq.,
          Kaufman & Canoles, for Communication Technologies, Inc., an intervenor.
          Capt. Ronald D. Sullivan, Maj. Howard W. Roth, Lt. Col. Scott E. Lind, and
          Col. Michael R. Neds, Department of the Army, for the agency.
          Paul E. Jordan, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          Protest that agency improperly failed to consider awardee's lower proposed fringe
          benefits in determining whether price proposal reflected management plan proposal
          to hire incumbent employees, is denied where source selection authority was aware
          of protester's higher fringe benefits and reasonably concluded that difference was
          not significant because awardee's overall proposed compensation, while lower than
          protester's, was comparable.
          DECISION

          MPRI, Inc. protests the award of a contract to Communication Technologies, Inc.
          (COMTek) under request for proposals (RFP) No. DABT60-01-R-0002, issued by the
          Department of the Army for Reserve Officer Training Corps (ROTC) functional
          support. MPRI challenges the evaluation of COMTek's proposal.

          The RFP sought proposals to provide nationwide specialized support in the
          functional areas of ROTC instruction, cadet recruiting, retention and training,
          administration, ROTC field training, and administrative and logistical services.
          Services included the provision of staff officers, assistant professors of military
          science (APMS), and enlisted instructors. Based on the prior history of
          performance, the agency anticipated a requirement of some 363 personnel at 220
          institutions. The RFP contemplated the award of a fixed-price requirements contract
          for a base year, with 4 option years.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most