         Decision


         Matter of: Reece Contracting, Inc.

         File:      B-285666

         Date:      August 21, 2000


         S. Leo Arnold, Esq., Ashley, Ashley & Arnold, for the protester.
         Robert M. Anderson, Esq., and Edward Goldstein, Esq., Army Corps of Engineers, for
         the agency.
         Christina Sklarew, Esq., and Paul I. Lieberman, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         Award based on bid that may have included unbalanced pricing is unobjectionable
         where agency's comparison of bids along with analysis of awardee's contract line
         item prices provided an appropriate basis for determination that the prices were
         reasonable and did not present an unacceptable level of risk to the government.
         DECISION

         Reece Contracting, Inc. protests the award of a contract to Merrick Construction Co.
         by the Army Corps of Engineers under invitation for bids (IFB) No. DACW38-00-B-
         0010 for a levee construction project. Reece alleges that Merrick's bid should have
         been rejected because it contained unbalanced pricing that presented the likelihood
         of an advance payment.

         We deny the protest.

         The IFB, issued in January 2000, sought fixed-price bids for the construction of
         levees, drainage structures, closure structures, and levee surfacing as part of a larger
         project in Catahoula Parish, Louisiana. The IFB listed 18 contract line item numbers
         (CLIN) for the work to be performed, and required bidders to submit lump-sum
         prices for certain CLINs and unit prices for others. Reece's protest is directed only
         at Merrick's prices for CLINs 0001 (mobilization and demobilization), 0002 (clearing
         and grubbing), 0003 (turfing), and 0008 (compacted fill).

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most