United States General Accounting Office           DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                             The decision issued on the date below was subject to a
                                                 GAO Protective Order. This redacted version has been
                                                 approved for public release.

         Decision

         Matter of: DUCOM, Inc.

         File:       B-285485

         Date:       August 23, 2000


         Lawrence J. Sklute, Esq., Sklute & Associates, for the protester.
         Cyrus E. Phillips, IV, Esq., for Z Systems Corporation, an intervenor.
         Joshua A. Kranzberg, Esq., and Wendy S. Saigh, Esq., Department of the Army, for
         the agency.
         Tania Calhoun, Esq., and Christine S. Melody, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         Protest that contracting agency improperly evaluated protester's technical proposal
         based on unstated evaluation factors and failed to evaluate offers on a common basis
         or otherwise unreasonably evaluated proposals is denied where record shows the
         evaluation was reasonable and consistent with solicitation's evaluation factors.
         DECISION

         DUCOM, Inc. protests the award of a contract to Z Systems Corporation under
         request for proposals (RFP) No. DAAE07-00-R-MO1O, issued by the Department of
         the Army's Tank-Automotive and Armaments Command (TACOM) to acquire Total
         Package Fielding (TPF) support services. DUCOM primarily argues that the agency
         improperly evaluated its technical proposal based on unstated evaluation factors and
         failed to evaluate offers on a common basis.

         We deny the protest.

         New weapons systems are accompanied by logistics support, such as auxiliary
         vehicles, spare parts, test and support equipment, vehicles, and technical manuals.
         The range and quantity of this logistics support increases the difficulty of getting that
         support to the user unit at the same time as the weapons systems. RFP § C-2-1. The
         TPF process minimizes the workload of the unit receiving the new weapons system
         by gathering the end item and all required support into a single package. This
         process is governed by Army Regulation AR-700-142, Materiel Release, Fielding and

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most