          G    A     0                                                  Comptroller General
             SIntegrity Reliability                                     of the United States
 ~ccountabthty Inert Rea iy
United States General Accounting Office             DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                   The decision issued on the date below was subject to a
                                                       GAO Protective Order. This redacted version has been
                                                       approved for public release.

          Decision

          Matter of: G&N, L.L.C.

          File:        B-285118; B-285118.2; B-285118.3

          Date:        July 19, 2000


          Albert B. Krachman, Esq., and Charles S. McNeish, Esq., Bracewell & Patterson, for
          the protester.
          William A. Roberts, III, Esq., and William Lieth, Esq., Wiley, Rein & Fielding, for
          BMAR & Associates, Inc., an intervenor.
          Larry E. Beall, Esq., U.S. Army Corps of Engineers, for the agency.
          Christina Sklarew, Esq., and Paul I. Lieberman, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          1. Where solicitation provides that technical proposals will receive highest possible
          score for fully satisfying the characteristics required in the solicitation and does not
          provide that additional credit will be given for exceeding the requirements, agency
          was not required to give additional evaluation credit to a proposal that may have
          exceeded the solicitation requirements.

          2. Protest that evaluation of technical proposals was unreasonable because it was
          inadequately documented is denied where the evaluation record, as clarified by
          narrative explanations provided by the agency, presents sufficient detail to assess
          the reasonableness of the conclusion that awardee's and protester's proposals were
          technically equivalent.
          DECISION

          G&N, L.L.C. protests the award of a contract to BMAR & Associates, Inc. under
          request for proposals (RFP) No. DACAO1-99-R-0049 issued by the Army Corps of
          Engineers for preventive maintenance and equipment inventory at healthcare
          facilities for the U.S. Medical Command (MEDCOM). G&N challenges the award on
          numerous grounds, primarily alleging that the Corps improperly evaluated proposals
          in a manner that was inconsistent with the RFP evaluation criteria and inadequately
          documented, and that the Corps accorded preferential treatment to the incumbent
          during the evaluation process by conducting prejudicially unequal discussions.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most