oComptroller General
             of the United States
             Washington, D.C. 20548
             Decision




             Matter of: Interstate Construction, Inc.

             File:       B-281465

             Date:        February 10, 1999

             Robert E. Thurbon, Esq., for the protester.
             Clark J. Hulce, Esq., Department of the Army, Corps of Engineers, for the agency.
             Susan K McAuliffe, Esq., and Christine S. Melody, Esq., Office of the General
             Counsel, GAO, participated in the preparation of the decision.
             DIGEST

             Bid imposing condition on performance is nonresponsive where it modifies material
             terms of the solicitation, limits contractor's liability to the government, and limits
             the rights of the government under the contract.
             DECISION

             Interstate Construction, Inc. protests the award of a contract to Kinley Construction
             Company under invitation for bids (IFB) No. DACA05-98-B-0026, issued by the
             Department of the Army, Corps of Engineers, Sacramento District, for the repair
             and upgrade of the jet fuel hydrant system and bulk fuel storage area at Beale Air
             Force Base, California. Interstate contends that Kinley's bid is nonresponsive, since
             it included a material condition on performance of the contract which may not be
             waived by the agency to make Kinley's bid responsive.

             We sustain the protest.

             The IFB, issued on August 12, 1998 and amended four times prior to the
             September 18 bid opening, sought bids for the repair and upgrade of the fuel
             hydrant system and fillstand. The solicitation's pricing schedule sought prices for
             seven basic items (Nos. 0001-0007) relating to repairs/upgrades at the Pumphouse
             No. 1 site, and two option items (Nos. 0008 and 0009) relating to repairs/upgrades at
             the bulk fuel storage area. IFB at 00010-5. Item No. 0009, relevant here and
             discussed more fully below, involves lowering the high-level shut-off valves on three
             bulk fuel storage tanks. Id. All major work items listed in the IFB (including all
             of the basic and option items in the pricing schedule) were to be included in a total
             lump-sum price for evaluation and award purposes. Id. at 00010-5, 01025-1,
             00100-13, and 00100-14.

             Twelve bids were received by bid opening. Kinley submitted the apparent low bid
             (at $1,591,566) and Interstate submitted the apparent second low bid (at $1,649,867).

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most