oComptroller General
             of the United States
             Washington, D.C. 20548
             Decision




             Matter of: Stanger Industries, Inc.

             File:       B-279380

             Date:       June 4, 1998

             Sharon K Stanger for the protester.
             Monica Allison Ceruti, Esq., Department of the Air Force, for the agency.
             Linda C. Glass, Esq., and Paul I. Lieberman, Esq., Office of the General Counsel,
             GAO, participated in the preparation of the decision.
             DIGEST

             Agency improperly rejected as nonresponsive a low bid that acknowledged all
             amendments to an invitation for bids (IFB), but used an unamended bid schedule
             which had been corrected by amendment to indicate that a requirement for periodic
             preventive maintenance should contain a monthly unit price entry and an extended
             price entry for the 9-month requirement rather than simply a lump-sum entry, where
             the bid commits the contractor to perform in accordance with the precise IFB
             requirements at the low price.
             DECISION

             Stanger Industries, Inc. protests the rejection of its bid under invitation for
             bids (IFB) No. F41689-98-B-0001, issued by the Department of the Air Force,
             Air Educational and Training Command Contracting Squadron, Randolph Air Force
             Base, Texas, for commissary refrigeration upgrade and periodic preventive
             maintenance and emergency repair for commissary refrigeration systems and
             heating ventilating and air conditioning systems at Hanscom Air Force Base,
             Massachusetts.

             We sustain the protest.

             The IFB, issued on November 17, 1997, contemplated the award of a fixed-price
             contract and contained a bid schedule listing five line items with a description of
             the required work, a quantity and unit designation, and spaces labeled unit price
             and amount for each item, along with one space calling for a total of the amount
             entries as the bid total. Line item No. 0002 was for providing all necessary
             equipment to perform the contract and line item No. 0003 was for periodic
             preventive maintenance in accordance with the solicitation requirement at section
             15995 that preventive maintenance commence 60 days after the notice to proceed
             was issued by the contracting officer and continue until 90 days after the final

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most