B-279251.2 1 (1998-06-01)

handle is hein.gao/gaocrptahsa0001 and id is 1 raw text is: 


oComptroller General
             of the United States
             Washington, D.C. 20548

             Decision                                 DOCUMENT FOR PUBLIC RELEASE
                                                    The decision issued on the date below was subject to a I
                                                    GAO Protective Order. This redacted version has been
                                                    approved for public release.



             Matter of: Exploration Products

             File:       B-279251.2; B-279251.3

             Date:       June 1, 1998

             Michael A. Hordell, Esq., and Laura L. Hoffman, Esq., Gadsby & Hannah, for the
             protester.
             Marian E. Sullivan, Esq., and P. Alan Luthy, Esq., Department of the Air Force, for
             the agency.
             John Van Schaik, Esq., and Michael R. Golden, Esq. Office of the General Counsel,
             GAO, participated in the preparation of the decision.
             DIGEST

             Selection of higher-priced proposal for small shelter/environmental control units
             was reasonable where testing of the protester's proposed equipment showed that
             the equipment did not meet a number of mandatory specifications.
             DECISION

             Exploration Products protests the award of a contract to Alaska Industrial
             Resources, Inc. under request for proposals (RFP) No. F08626-97-R-0107, issued by
             the Department of Air Force for a quantity of small shelter/environmental control
             units (SS/ECU). Exploration argues that its SS/ECU was not properly evaluated and
             that the Air Force should have communicated with the firm concerning certain
             failures of its equipment during government testing.

             We deny the protest because Exploration's SS/ECU was unacceptable and
             Exploration could not be awarded the contract due to its failure to meet certain
             mandatory specifications.

             The RFP stated that the objective of the contract is to procure a commercially-
             available, nondevelopmental shelter and ECU to replace the agency's current
             shelters for housing and work areas and that the primary focus is to acquire a
             system that is less of a burden to transport than the current SS/ECU. The RFP
             included a System Performance Specification which described the performance
             requirements and physical characteristics of the new SS/ECU. That document
             stated, at section 1.1, that [t]he primary objective of the specification is to outline
             the performance and physical characteristic requirements for a new system that

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most