B-276434 1 (1997-06-12)

handle is hein.gao/gaocrptafyk0001 and id is 1 raw text is: 


oComptroller General
             of the United States
             Washington, D.C. 20548
             Decision                                DOCUMENT FOR PUBLIC RELEASE

                                                    A protected decision was issued on the date below
                                                    and was subject to a GAO Protective Order. This
                                                    version has been redacted or approved by the parties
                                                    involved for public release.


             Matter of: Marvin Land Systems, Inc.

             File:       B-276434; B-276434.2

             Date:       June 12, 1997

             William A. Roberts III, Esq., Lee P. Curtis, Esq., and Richard P. Castiglia Jr., Esq.,
             Howrey & Simon, for the protester.
             Joel R. Feidelman, Esq., Anne B. Perry, Esq., and Nancy R. Wagner, Esq., Fried,
             Frank, Harris, Shriver & Jacobson, for Napco International, Inc., an intervenor.
             Vera Meza, Esq., and Robert A. Maskery, Esq., Department of the Army, for the
             agency.
             Guy R. Pietrovito, Esq., and James A. Spangenberg, Esq., Office of the General
             Counsel, GAO, participated in the preparation of the decision.
             DIGEST

             Where protester challenges exclusion from consideration for the award of a
             reprocurement contract, protest is denied as to base quantity, because agency
             reasonably determined that only the awardee could satisfy its requirements for the
             base quantity within the time required.
             DECISION

             Marvin Land Systems, Inc. protests the sole source award of contract No. DAAE07-
             97-C-X065 to Napco International, Inc. by the U.S. Army Tank-automotive and
             Armaments Command (TACOM) for M113A3 conversion kits. The contract is a
             reprocurement of a requirement that had been previously awarded to Kit Pack
             Company; Kit Pack's contract was terminated for default. Marvin contends that the
             agency had no reasonable basis to exclude it from consideration for award of this
             requirement.

             We deny the protest.

             The M113A3 conversion kits are necessary to support ongoing upgrades at Anniston
             Army Depot, Alabama, and Bokuk Industries, Guji, Korea of the M113 Family of
             Vehicles (the M113 Armored Personnel Carrier, M577 Command Post Vehicle,
             M1068 Standard Integrated Command Post Systems, M58 Smoke, Opposing Forces
             Surrogate Vehicle, and M1064 120MM Mortar System). The kits contain more than
             1,100 different parts, several of which (such as the armor plate, transmission
             controller, and variable speed fan drive) are long-lead items.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most