B-275181 1 (1997-01-29)

handle is hein.gao/gaocrptaftq0001 and id is 1 raw text is: 


Comptroller General
of the United States
Washington, D.C. 20548
Decision                                  DOCUMENT FOR PUBLIC RELEASE

                                         A protected decision was issued on the date below
                                         and was subject to a GAO Protective Order. This
                                         version has been redacted or approved by the parties
                                         involved for public release.


Matter of: Cygnus Corporation

File:        B-275181

Date:        January 29, 1997

William M. Rosen, Esq., Hilary S. Cairnie, Esq., and Edward W. Kirsch, Esq.,
Dickstein Shapiro Morin & Oshinsky, for the protester.
Eric M. Drattell, Esq., David R. Johnson, Esq., and Robert J. Rothwell, Esq.,
McDermott, Will & Emery, for Caliber Associates, Inc., an intervenor.
Terrence J. Tychan and Michael Colvin, Department of Health and Human Services,
for the agency.
Ralph 0. White, Esq., and Christine S. Melody, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST

1. New and independent grounds of protest included in a protester's comments on
the agency report must independently meet the timeliness requirements of the
General Accounting Office's Bid Protest Regulations; extensions of time for filing
comments do not waive the timeliness requirements.

2. Protester's contentions that the awardee failed to advise the agency that its
project director would not be available at the start of contract performance and
used an improper bait and switch practice by allowing other employees to
substitute for the proposed project director in the first 3 weeks of contract
performance is denied where the record shows that the proposal clearly advised the
agency that the project director was a contingent hire; the awardee did, in fact, hire
the proposed project director as promised; and the project director began work
within 3 weeks of contract award.

3. Allegation that agency evaluation of protester's best and final offer (BAFO) was
unreasonable is sustained where the record as a whole supports the conclusion that
the agency did not meaningfully evaluate certain key material in the BAFO.
DECISION

Cygnus Corporation protests the award of a contract to Caliber Associates, Inc.
under request for proposals (RFP) No. 105-96-1648, issued by the Department of
Health and Human Services for the operation and management of the National


41126

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most