B-417752, B-417752.2, B-417752.3 1 (2019-10-17)

handle is hein.gao/gaobaeacp0001 and id is 1 raw text is: 



GAO U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                             of the United States
                                          .......................................................................................................................
                                             DOCUMENT FOR PUBLIC RELEASE
                                           The decision issued on the date below was subject to
Decision                                   a GAO Protective Order. This redacted version has
                                           been approved for public release.


Matter of:   NCI Information Systems, Inc.

File:        B-417752; B-417752.2; B-417752.3

Date:        October 17, 2019

David Cohen, Esq., Cordatis LLP, for the protester.
Jonathan D. Shaffer, Esq., Todd M. Garland, Esq., Mary Pat Buckenmeyer, Esq., Smith
Pachter McWhorter PLC, for the intervenor.
Wade L. Brown, Esq., and Dylan C. Bush, Esq., U.S. Army Materiel Command, for the
agency.
Christopher Alwood, Esq., and Christina Sklarew, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST

1. Protest challenging an agency's evaluation of proposals under the technical
evaluation factor is denied where the evaluation was reasonable and the agency's
assessment of adjectival ratings was consistent with the solicitation.

2. Protest challenging an agency's evaluation of protester's and awardee's proposals
under the cost/price evaluation factor is denied where the evaluation was reasonable,
including the agency's interpretation of a solicitation provision allowing offerors to
submit documentation in addition to what the solicitation explicitly required to support
proposed indirect rates.

3. Protest challenging agency's best-value tradeoff determination is denied where the
record reflects that the contracting officer reasonably found the proposals of the
awardee and the protester to be technically equal and selected the lower-priced
proposal for award.
DECISION

NCI Information Systems, Inc. (NCI), of Reston, Virginia, protests the issuance of a task
order to AECOM Management Services, Inc. (AECOM), of Germantown, Maryland,
pursuant to request for proposals (RFP) RS3-18-R-0078, issued by the Department of
the Army for systems engineering and technical assistance services. NCI challenges
various aspects of the agency's source selection process, including the agency's
evaluation under the technical and cost/price factors.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most