B-413974.3 1 (2017-06-15)

handle is hein.gao/gaobadtwa0001 and id is 1 raw text is: 



GO U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                             of the United States
                                                      --------------------------------------------------------------------------------------------------------------------.
                                                          DOCUMENT FOR PUBLIC RELEASE
                                                        The decision issued on the date below was subject to
Decision                                                a GAO Protective Order. This redacted version has
                                                        been approved for public release.
                                                      ......................................................................................................................

Matter of:   Synergy Solutions, Inc.

File:        B-413974.3

Date:        June 15, 2017

Isaias Alba, IV, Esq., Kathryn V. Flood, Esq., Michelle E. Litteken, Esq., Julia Di Vito,
Esq., and Marc B. Langston, Esq., Piliero Mazza PLLC, for the protester.
Amy Laderberg O'Sullivan, Esq., Olivia L. Lynch, Esq., and Laura J. Mitchell Baker,
Esq., Crowell & Moring LLP, for TUVA, LLC, the intervenor.
William Mayers, Esq., Department of Energy, for the agency.
Katherine I. Riback, Esq., and Amy B. Pereira, Esq., Office of the General Counsel,
GAO, participated in the preparation of the decision.
DIGEST

1. Protest that the agency's cost realism evaluation of the awardee's proposed costs
was unreasonable is denied where the agency's evaluation was reasonable and
supported by the record.

2. Protest challenging portions of the agency's evaluation of proposals is dismissed as
untimely where the protester could have and should have raised the protest grounds
during the prior protest.

3. Protest challenging agency's technical and past performance evaluation is denied,
where the agency evaluated the proposals in accordance with the terms of the
solicitation.
DECISION

Synergy Solutions, Inc., (Synergy) of Oak Ridge, Tennessee, a small business, protests
the award of a contract by the Department of Energy, National Nuclear Security
Administration, under request for proposals (RFP) No. DE-SOL-0006736 to TUVA, LLC,
of Herndon, Virginia, for services in support of the Office of Personnel and Facility
Clearances at Kirtland Air Force Base in Albuquerque, New Mexico. Synergy
challenges the agency's evaluation under the cost and non-cost factors, and maintains
that the agency failed to conduct meaningful and equal discussions.


We deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most