B-409681.3,B-409681.4 1 (2015-10-21)

handle is hein.gao/gaobadrpd0001 and id is 1 raw text is: 




         G    A    O                                                    Comptroller General
      Accountabilty * Integrity * Reliability                           of the United States
United States Government Accountability Office  D~OCUMENT FOR PUBLIC RELEASE
Washington, DC 20548
                                                     The decision issued on the date below was subject to
                                                     a GAO Protective Order. This redacted version has
         Decision                                  I been approved for public release.




         Matter of:   McConnell Jones Lanier & Murphy, LLP

         File:        B-409681.3; B-409681.4

         Date:        October 21, 2015

         G. Lindsay Simmons, Esq., J. Eric Whytsell, Esq., Hopewell H. Darneille, Esq., and
         Lara Nochomovitz, Esq., Jackson Kelly PLLC, for the protester.
         Patricia H. Wittie, Esq., Wittie Law, PLLC, for Alternate Perspectives, Inc., an
         intervenor.
         David R. Koeppel, Esq., Dennis A. Adelson, Esq., and Savannah L. Wilson, Esq.,
         Department of Labor, for the agency.
         Louis A. Chiarella, Esq., and Nora K. Adkins, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         1. Protest that the agency engaged in misleading discussions that led the protester
         to increase its cost is denied where the protester's contention is not supported by
         the record, and where the protester made its own independent business judgment
         to adjust its proposed cost.

         2. Protest challenging the agency's technical evaluation is denied where the
         evaluation was reasonable and consistent with the stated evaluation criteria.

         3. Protest challenging the agency's evaluation of past performance is denied where
         the evaluation was reasonable and consistent with the solicitation's stated
         evaluation criteria, and the protester failed to demonstrate that it was prejudiced by
         any alleged error.

         4. Protest that agency failed to give adequate consideration to awardee's potential
         organizational conflicts of interest (OCI) is denied, where the protester's assertions
         fail to present hard facts indicating the existence of a conflict.
         DECISION

         McConnell Jones Lanier & Murphy, LLP (MJLM), of Houston, Texas, protests the
         award of a contract to Alternate Perspectives, Inc. (API), of Leesburg, Virginia,
         under request for proposals (RFP) No. DOL12QA20003, issued by the U.S.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most