About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

B-411745 1 (2015-10-08)

handle is hein.gao/gaobadroc0001 and id is 1 raw text is: 




         G    A    O                                                    Comptroller General
      Accountability * Integrity * Reliability                          of the United States
United States Government Accountability Office   DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to
                                                     a GAO Protective Order. This redacted version has
                                                     been approved for public release.
         D e  c i s i o n                          - .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


         Matter of:   National O&M, Inc.

         File:        B-411745

         Date:        October 8, 2015

         Jennifer S. Zucker, Esq. and John R. Prairie, Esq., Wiley Rein LLP, for the
         protester.
         Christopher S. Cole, Esq., Department of the Air Force, for the agency.
         Robert T. Wu, Esq., and Tania Calhoun, Esq., Office of the General Counsel, GAO,
         participated in the preparation of the decision.
         DIGEST

         Protest that the agency improperly evaluated the awardee's proposal as technically
         acceptable is denied where the record shows that the agency's evaluation was
         reasonable and consistent with the solicitation's terms.
         DECISION

         National O&M, Inc., of Roanoke, Virginia, protests the award of a contract to Project
         Solutions, Inc. (PSI), of Rapid City, South Dakota, by the Department of the Air
         Force under request for proposals (RFP) No. FA4855-15-R-0002 for wastewater
         treatment plant services. National argues that the agency unreasonably found
         PSI's proposal to be technically acceptable.

         We deny the protest.

         BACKGROUND

         The RFP, issued on April 22, 2015, sought proposals for operation, inspection,
         maintenance, and repair services at a wastewater treatment plant located on
         Cannon Air Force Base, New Mexico. RFP at 3. The RFP contemplated the award
         of a fixed-price contract for one nine-month base period and four 1-year options. Id.
         at 3-7. Proposals were to be evaluated on a lowest-priced, technically acceptable
         basis, considering price and technical capability. Id. at 15. Technical capability
         included two subfactors: technical proficiency and mission essential contractor
         services plan. Id. at 16. Ratings of acceptable or unacceptable were to be
         assigned to each subfactor and to the technical capability factor. A rating of

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most