B-410220 1 (2014-11-17)

handle is hein.gao/gaobadqtp0001 and id is 1 raw text is: 




         G    A    O                                                   Comptroller General
      Accountabilty * Integrity * Reliability                          of the United States
United States Government Accountability Office   DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                The decision issued on the date below was subject to
                                                    a GAO Protective Order. This redacted version has
                                                    been approved for public release.
         D e  c i s i o n                          L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


         Matter of:   Sea Box, Inc.

         File:        B-410220

         Date:        November 17, 2014

         Pamela J. Mazza, Esq., Kathryn V. Flood, Esq., Peter B. Ford, Esq., Megan C.
         Connor, Esq. and Brian F. Wilbourn, Esq., PilieroMazza PLLC, for the protester.
         Michael J. Kraycinovich, Esq., and Russell W. Bottom, Esq., U.S. Army Materiel
         Command, for the agency.
         Susan K. McAuliffe, Esq., and Edward Goldstein, Esq., Office of the General
         Counsel, GAO, participated in the preparation of the decision.
         DIGEST

         1. Protest of technical evaluation is denied where record shows that it was
         reasonable and consistent with the terms of the solicitation.

         2. Under solicitation contemplating award of fixed-price contract, protest
         challenging agency's price realism analysis is denied where the record reflects that
         the agency evaluated the underlying cost elements of the awardee's lower price and
         the protester has not shown that the agency's consideration of this information was
         unreasonable.
         DECISION

         Sea Box, Inc., of East Riverton, New Jersey, protests the award of a contract to
         Berg Manufacturing, Inc., of Spokane, Washington, by the Department of the Army
         under request for proposals (RFP) No. W90985-14-R-0002 for metal working and
         machining shop set (MWMSS) shelters. Sea Box contends that the agency's
         evaluation of the awardee's proposal was improper.

         We deny the protest.

         BACKGROUND

         The RFP, a small business set-aside issued on January 31, 2014, anticipated the
         award of a 5-year indefinite-delivery, indefinite-quantity contract for 1-sided
         expandable shelters. RFP at 2-3. The contract was to be awarded on a fixed-price

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most