B-408775 1 (2013-12-04)

handle is hein.gao/gaobadpyb0001 and id is 1 raw text is: 




         G    A    O                                                    Comptroller General
      Accountabilty * Integrity * Reliability                           of the United States
United States Government Accountability Office   DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to
                                                     a GAO Protective Order. This redacted version has
                                                     been approved for public release.
         D e  c i s i o n                          L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


         Matter of:   JAM Corporation

         File:        B-408775

         Date:        December 4, 2013

         Theodore P. Watson, Esq., and Nicole Lynn Carter, Esq., Watson & Associates,
         LLC, for the protester.
         Gregory S. Jacobs, Esq., and Erin L. Felix, Esq., Reed Smith LLP, for American
         Engineering Corporation, the intervenor.
         C. Scott Vogeley, Esq., United States Marine Corps, for the agency.
         Kenneth Kilgour, Esq., and David A. Ashen, Esq., Office of the General Counsel,
         GAO, participated in the preparation of the decision.
         DIGEST

         1. Protest that agency improperly evaluated proposals is denied where the record
         shows that the agency's evaluation was reasonable and in accordance with the
         terms of the solicitation and applicable procurement statutes and regulations.

         2. Agency's determination that protester's cited contract did not meet the
         solicitation's 3-year recency requirement for consideration in the past performance
         evaluation reasonably relied upon protester's own indication in its proposal of the
         contract end date to determine that the contract was not recent, notwithstanding the
         protester's unsupported claim that the agency should have known that the contract
         extended for an unspecified period after the end date reported in the protester's
         proposal.
         DECISION

         JAM Corporation, of Okinawa, Japan, protests the U.S. Marine Corps's (USMC)
         award of a contract to American Engineering Corporation (AEC), of Okinawa,
         Japan, under request for proposals (RFP) No. M67400-13-R-0003, for corrosion
         control and repair services for government-owned equipment at Camp Kisner,
         Okinawa, Japan. The protester challenges the evaluation of technical proposals
         and the best value trade-off decision.


We deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most