          SG    A    O                                                   Comptroller General
Accountability * Integrity * Reliability                                 of the United States
  United States Government Accountability Office    DOCUMENT FOR PUBLIC RELEASE
  Washington, DC 20548                                The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.
           D  e c i s i o n                          L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


           Matter of:  Weibel Equipment, Inc.

           File:       B-406888; B-406888.2

           Date:       September 21, 2012

           Thomas M. Brownell, Esq., Terry Elling, Esq., and Gregory Hallmark, Esq., Holland
           & Knight LLP, for the protester.
           Kevin C. Dwyer, Esq., Kathy C. Weinberg, Esq., Damien C. Specht, Esq., and
           Carrie F. Apfel, Esq. Jenner & Block LLP, for General Dynamics C4 Systems, the
           intervenor.
           Tina Pixler, Esq., and Bryan C. Naquin, Esq., Department of the Army, for the
           agency.
           Eric M. Ransom, Esq., and Edward Goldstein, Esq., Office of the General Counsel,
           GAO, participated in the preparation of the decision.
           DIGEST

           1. Protest challenging agency's evaluation of awardee's past performance and
           protester's technical proposal is denied where the record shows that the evaluation
           was consistent with the terms of the solicitation and reasonable.

           2. Protest that agency failed to properly consider information contained in the
           protester's final proposal revision is denied where the protester was not prejudiced
           by the agency's error.
           DECISION

           Weibel Equipment, Inc., of Lansdowne, Virginia, protests the award of a contract to
           General Dynamics C4 Systems, of Scottsdale, Arizona, by the Department of the
           Army, Program Executive Office for Simulation, Training, and Instrumentation,
           under request for proposals (RFP) No. W900KK-1 1 -R-0034, for the Army's Range
           Radar Replacement Program.


We deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most