B-406057,B-406057.2,B-406057.3,B-406057.4 1 (2012-02-01)

handle is hein.gao/gaobadook0001 and id is 1 raw text is: 



           G   A    O                                                   Comptroller General
Accountability * Integrity * Reliability                                 of the United States
United States Government Accountability Office  DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548
                                                      The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has

          D e c is io n                               [L been appovedforpublic release ----------.

          Matter of:   Baltimore Gas and Electric Company

          File:     B-406057; B-406057.2; B-406057.3; B-406057.4

          Date:     February 1, 2012

          Richard P. Rector, Esq., Seamus Curley, Esq., C. Bradford Jorgensen, Esq., Dionis
          M. Gauvin, Esq., and Nedra S. Adams, Esq., DLA Piper US LLP, for the protester.
          Timothy E. Heffernan, Esq., Bennett Lee, Esq., Nicholas A. Merrell, Esq., and
          Regina A. Verducci, Esq., Watt, Tieder, Hoffar & Fitzgerald, LLP, for City Light &
          Power, Inc., the intervenor.
          Joshua S. Bartz, Esq., and Paul R. Hahn, Esq., Defense Logistics Agency, for the
          agency.
          Nora K. Adkins, Esq., and James A. Spangenberg, Esq., Office of the General
          Counsel, GAO, participated in the preparation of the decision.
          DIGEST

          1. Agency reasonably calculated its government should cost estimate used in the
          economic analysis required by 10 U.S.C. § 2688 (2009) to determine whether the
          privatization of an electric utility system would reduce the long-term cost to the
          government of the utility system. Based on this economic analysis, the agency
          reasonably concluded that the awardee's proposal provided the required long-term
          cost reduction, and determined that the protester was ineligible for award because
          its proposal did not reduce the long-term cost to the government.

          2. Protest that the agency unreasonably determined the protester's technical
          capability was unacceptable and high in risk is denied, where the record shows the
          agency reasonably determined that the protester's plans to perform the work were
          unacceptable and that its performance risk and cost realism risks were high.
          DECISION

          Baltimore Gas and Electric Company (BGE), of Baltimore, Maryland, protests the
          award of a contract to City Light and Power, Inc. (CLP), of Long Beach, California,
          by the Defense Logistics Agency (DLA) under request for proposals (RFP)
          No. SP0600-08-R-0804, for privatization of the electric distribution system at the
          Aberdeen Proving Ground in Edgewood, Maryland.


We deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most