B-405589 1 (2011-11-23)

handle is hein.gao/gaobadokk0001 and id is 1 raw text is: 




A         G     A     0                                                 Comptroller General
lAccoauntability * Integrity * Reliability                              of the United States
  U n ited  S ta tes  G ov ern m e n t  A cco u n tab ility  O ffice  ----------------------------------------------------------------------------------------------------------------------
  Washington, DC 20548                                 DOCUMENT FOR PUBLIC RELEASE
                                                      The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
           Decision                                   approved for public release.



           Matter of. NCI Information Systems, Inc.

           File:       B-405589

           Date:       November 23, 2011

           Daniel S. Herzfeld, Esq., John E. Jensen, Esq., Evan D. Wesser, Esq., and Nicole Y.
           Beeler, Esq., Pillsbury Winthrop Shaw Pittman LLP, for the protester.
           Captain Edward Aln, Department of the Army, for the agency.
           Jonathan L. Kang, Esq., and James A. Spangenberg, Esq., Office of the General
           Counsel, GAO, participated in the preparation of the decision.
           DIGEST

           1. Protest challenging the agency's use of information from awardee's performance
           of the incumbent contract in the development of the independent government cost
           estimate, which was used in evaluating offerors' staffing approaches and prices, is
           denied because the use of this information, in conjunction with other data, was not
           inappropriate.

           2. Protest challenging the agency's conclusion that the protester's staffing approach
           contained significant weaknesses is denied where the protester's proposed staffing
           for several functions was reasonably determined to be insufficient.

           3. Protest that agency failed to conduct meaningful discussions with the protester
           concerning its proposed staffing in a task order competition conducted under
           Federal Acquisition Regulation Part 16 is denied where the record shows that the
           agency reasonably advised the protester of significant weaknesses in its proposal
           that required improvement.
           DECISION

           NCI Information Systems, Inc., of Reston, Virginia, protests the issuance of a task
           order to Lockheed Martin Integrated Systems, of Alexandria, Virginia, by the
           Department of the Army, Mission Installation Contracting Command, under request
           for task order response (RTOR) No. W91247-10-ITES-0002, for information
           technology (IT) support services at the Army's Network Enterprise Center (NEC) at

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most