handle is hein.gao/gaobadoib0001 and id is 1 raw text is: 



J         G    A                                                          Comptroller General
        Accountability * Integrity * Reliability                           of the United States
United States Government Accountability Office  DOCUMENTFoR-PUBICRELEASE
Washington, DC 20548                                   The decision issued on the date below was subject to
                                                       a GAO Protective Order. This redacted version has
                                                       been approved for public release.

          Decision

          Matter of:   Data Solutions & Technology, Inc.

          File:        B-405077.2

          Date:     October 12, 2011

          Deborah S. Thomas, Data Solutions & Technology, Inc., for the protester.
          Maj. Andrew J. Smith, Department of the Army, for the agency.
          Linda C. Glass, Esq., and Sharon L. Larkin, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Protester's contention that its proposal was improperly excluded from the
          competitive range is denied where the protester has not shown that the agency's
          evaluation was unreasonable or inconsistent with the stated evaluation criteria.
          DECISION

          Data Solutions & Technology, Inc. (DST), of Lanham, Maryland, protests the
          elimination of its proposal from the competitive range by the Department of the Army
          under request for proposals (RFP) No. W9124J-1 1-R-0001 for base support services
          at various Army installations. DST challenges the evaluation of its proposal.

          We deny the protest.

          BACKGROUND

          The RFP was issued on December 7, 2010 and contemplated the award of an
          indefinite-delivery/indefinite-quantity contract for a 12-month period with four
          12-month option periods. The RFP provided for a best value source selection
          decision on the basis of the following evaluation factors: mission capability; past
          performance; and cost/price. RFP at 95-96. The mission capability factor was
          significantly more important than past performance and was divided into the
          following five subfactors: response to scenario; management approach; staffing and
          training approach; quality approach; and technical expertise. Id. The first subfactor,
          response to scenario, was significantly more important than the four remaining
          subfactors, which were of equal importance, and when combined, were equal in
          weight to the first subfactor. Id.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most