B-204728 1 (1981-09-29)

handle is hein.gao/gaobadjtx0001 and id is 1 raw text is: 



                                       THE dOMPTROLLER GENERAL
               DECISI|O        * i*dl,' OF T HE UN ITE      STATE S
                                       WASHINGTON, D.C        20548




               FILE: B-204728                DATE: September 29, 1981

               MATTER OF: Abney Construction Company Incorporated


               DIGEST:


               1. Contractor under pre-March 1, 1979, contract
                   has right to have claim, pending as of that
                   date before the contracting officer or
                   initiated thereafter, processed under Contract
                   Disputes Act of 1978 or under disputes clause
                   of contract.

               2. Contractor under pre-March 1, 1979, contract
                   has requested GAO review of claim, pending
                   before contracting officer on March 1, 1979,
                   which was finally denied on March 23, 1979.
                   If contractor under facts of record has
                   consciously elected to have claim processed
                   under act rather than under contract's disputes
                   clause, GAO may not consider claim since
                   consideration would afford contractor a forum
                   it would otherwise not have. Alternatively,
                   if contractor has elected to have claim
                   processed under the disputes clause, GAO may
                   still not review claim to the extent a disputed
                   question of fact exists as is involved in the
                   subject claim.


                   Abney Construction Company (Abney) has requested
               reconsideration of the settlement certificate issued
               by our Accounting and Financial Management Division,
               Claims Group, on August 19, 1981, which disallowed its
               claim for costs related to damage to a transformer
               which was struck by lightning on September 2, 1977.
               The disallowance noted that a dispute concerning a
               question of fact existed as to when the United States
               assumed control of the transformer under Abney's
               contract No. N62467-74-C-0562, dated June 23, 1976,
               with the Department of the Navy.

                    The record shows Abney's claim was finally decided
               by the Navy's contracting officer by letter of March 23,

I

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most