B-190073 1 (1977-11-23)

handle is hein.gao/gaobadfkd0001 and id is 1 raw text is: 







                               6P         ' THE COMPTROLLER GENERAL
              DECIBIOI .' :               OF   THr- UNITED         ETATUE
                                          WAHINGTON, D.C. 2f354e


r_4
-*           FILE:     B-190073                  DATE:   November 23, 1977

o)           MATTER OF'         Harvey Bell


             DIGEST:

               1.  Determination tc cancel invitation and to resolicit
                   requirement was proper where invitation contaic-d con-
                   tradictory (90 and 120 days) contract completion schedule
                   requirements, low bidder bid on the 120-day requirement
                   (the activity intended to require 90-day completion) and
                   other bidders either bid on 90-day requirement or basis
                   they bid on is unclear, Atnce ambiguity kept bidders from
                   bidding on equal basis.

               2.  Fact that no bidder made request for clarification of
                   ambiguous IFB terms prior to bid opening does not preclude
                   contracting officer from canceling IFB where such ambiguity
                   is brought to his attentinn prior to award.


                   harvey Bell protests the cance'lation of invitation fo:: bid:;
               (IFB) No. R4-77-73 after bid opening and the readvertisemen: of
               that procurement by the United States Forest Service.

                   The invitation tias caficeled so that conflictIng la;guage
              in the IFB regarding the iequired contract completion period
              might be clarified.  On Standard Form 20 of the original invita-
              tion it was provided that All work Is to be completed within
              120 days after date of receipt of Notice to Proceed. On Standa-d
              Form 21, also a part of the invitation, it was provided that The
              undersigned agrees * * * to complete the work within 90 calendar
              days after the date of receipt of Notice to Proceed. The
              90-calendar-day period was the one the contracting activity
              desired.

                   Upon bid opening and after a perusal of the Plan an '.
              Equipment Questionnaire submitted by each bidder with its bid,
              it was noticed that two of the bidders (one the low bidder) had
              apparently relied on the 120-day figure. A third bidder had
              relied on a 90-day completion schedule, and it tAs impossible to
              tell what completion schedule the remaining bidders had contem-
              plated when computing their bids. Because all bidders had there-
              fore not bid on an equal basis the contracting officer believed a



                                            - 1-

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most