B-184904 1 (1975-12-30)

handle is hein.gao/gaobaddtx0001 and id is 1 raw text is: 

                              THE   COMPTROLLER GENERAL
 DECISION         .         . OF   THE UNITED          STATES
                            ,jWASHINGTON, 0. C. 20546B




 FILE:   B-184904                    DATE:   December 30,1975

 MATTER OF:       Imperial Eastman Corporation


 DIGEST:

     Where IFB required delivery within 280 days after date of
     award, telegraphic bid offering delivery 280 days after
     receipt of award was properly rejected as nonresponsive,
     where solicitation contained provision for evaluation of
     bids offering delivery based upon date of receipt of con-
     tract or notice of award (rather than contract date) by
     adding the maximum number of days normally required for
     delivery of the award through the mails. Thus evaluated,
     protester's bid exceeded the required delivery schedule.


     Imperial Eastman Corporation (Imperial) has protested the
rejection of its low telegraphic bid as nonresponsive, and the
subsequent award of a contract to Container Service, Inc. (CSI),
the second low bidder, under invitation for bids No. DSA700-75-
B-2685, issued by the Defense Supply Agency, Defense Construction
Supply Center (DCSC), Columbus, Ohio.

     The subject IFB, which called for the supply of tube-pipe
fitting kits, required delivery within 280 days after date of
award.  Upon the opening of bids on July 30, 1975, it was dis-
covered that Imperial's low telegraphic bid stated, in part,
delivery terms of 280 days after receipt of award /emphasis
added7.  However, a signed bid form, which was received as a con-
firming bid after the time set for bid opening, took no exception
to the IFB's delivery requirements. The agency advised Imperial
that the confirming bid could not be considered in determining
the responsiveness of the timely telegraphic bid due to its
untimely receipt.  The timely telegraphic bid was rejected as
nonresponsive pursuant to Armed Services Procurement Regulation
(ASPR) @ 2-404.2(c)(1974 ed.) which requiresrejection of any bid
which fails to conform to the delivery schedule.

     Counsel for Imperial has contended that the bid was
improperly rejected and that the contracting officer failed to
follow the procurement regulations applicable to an apparent
minor informality, irregularity, or mistake in bid.

                                                     PUDLISHED DECISION
                                                     b5 Comp. Gen.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most