handle is hein.gao/gaobaddje0001 and id is 1 raw text is: 



                    0LR C
                    00     . THE  COMPTROLLER GENERAL
DECISION                     OF   THE UNITED STATEs
                             WASHINGTON, D.C. 20548




FILE:  B-185032                     DATE:  August 3, 1976

MATTER OF: Robert McMullan & Son, Inc.                      -


DIGEST:


     Procuring activity has not designated its Base Communications
     Center as place for receipt of written notice of bid mistakes
     merely because all its telegraphic messages are routed through
     Center.  Prior decision denying upward adjustment in contract
     price on basis that notice of bid mistake was not received by
     Government until after award was made is sustained.

     Robert McMullan & Son, Inc., has requested reconsideration of
our decision, B-185032, March 18, 1976, 76-1 CPD 185 denying its
claim for an upward price adjustment in its contract with the Depart-
ment of the Navy, Naval Facilities Engineering Command (Engineering
Command) No. N62467-73-C-0073.

     The Navy issued a solicitation for the construction of barracks
and the modernization and additions to mess facilities at the
Charleston Naval Station and McMullan was the low bidder. Between
bid opening date, June 5, 1975, and award date, June 30, 1975,
McMullan discovered that it had mistakenly concluded that a
supplier's quote included both labor and materials, when, in fact,
the quote covered only labor costs. McMullan attempted to inform
the contracting officer of its mistake on June 30, 1975 by dis-
patching a TWX message addressed to the Engineering Command, the
place designated in the solicitation for receipt of pre-bid opening
withdrawals.  The TWX arrived at a nearby Navy Communications .Center
on June 30, 1975, but was not delivered to the Engineering Command
until the following day, after the award was made. This Office
found that McMullan's notice of mistake was not received by the
Engineering Command until July 1, 1975, and that notice of award
to McMullan was mailed on June 30, 1975. We held that since the
notice of mistake and withdrawal was not received by the Engineering
Command until after award had been made, the contracting officer
did not have notice of mistake and consequently a valid and binding
contract exists at the award price.

     McMullan now contends that our decision does not follow from
 the facts presented; that the Navy's credibility is suspect because
 of misstatements in its report to this Office that McMullan's TWX
 message was timely delivered to the Charleston Naval Base Communica-
 tions Center on June 30, 1975, and that, even if receipt at the


- 1 -

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most