B-183915 1 (1975-06-27)

handle is hein.gao/gaobadcgy0001 and id is 1 raw text is: I.


                    0 LElt~.
                             THE   C  MPT,1OLLER GENERAL
                   a7~ .OF THE           UNITED       STATES
                             WASHINGTON, D. C. 20548



                                                               ?7/ 5c,
FILE:  B-183915                     DATE:    June 25, 1975

MATTER OF: Defense Mapping Agency


DIGEST:

     Where Government has received and retained benefit of repair
     parts ordered by its employee who lacked authority to do so,
     contractor, having acted in good faith, may be paid on guan-
     -tum valebant basis in accordance with agency recommendation.


     This decision to the Accounting and Finance Officer, Defense              /
Mapping Agency, is in response to a request for a decision pur-
suant to 31 U.S.C. 74 as to the legality of payment for items to
be used with survey equipment of the Defense Mapping School. These
items were ordered during the period of October 23 through
November 11, 1974, without an authorizing purchase order from Sur-
veying and Engineering Supply Company, in a total amount of $6,599.01.

     The Defense Mapping Agency has indicated that there was an
immediate requirement for the items ordered which the noncommis-
sioned officer who placed the orders perceived as sufficiently
urgent to justify proceeding informally. In addition, the officer
believed that he had received permission to purchase the items
because the items were to be purchased on a sole source basis
and purchasing orders, he believed, were forthcoming. Although
no purchase orders were in fact forthcoming, it is reported that
an authorized procurement was in the process of being finalized.

     This situation was discovered during an internal audit and
all outstanding orders with the vendor were cancelled. It is
reported that internal controls have been established to prevent
a recurrence of such unauthorized procurement actions. All items
received have been distributed to various divisions where they have
been or are in the process of being used for repairs. The account-
ing and finance officer has recommended that full payment be made.

     Although the United States cannot be bound beyond the actual
authority conferred upon its agents by statute or regulation, see
United States v. Crance, 341 F. 2d 161, 166 (1965), the courts and
our Office have recognized that in appropriate circumstances payment


- 1 -

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most